| CONSTRUCTION OF NEW TENNIS CENTER BUILDING |
| |
| |
| |
| 7/22/20 REACTIVATED PER RB SH |
| 4/20/18 SARAH DID CHANGE OF CONTRACTOR RES |
| 3/2/18 STEPHEN P/U PERMIT SPALMWER |
| 3/2/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
| READY TO BE PICKED UP, FILED UNDER LARGE "M". CP |
| 2/28/18 PLUMBING APPROVED RETURN TO C02/GPJ |
| 2/15/18 REQUEST FOR EXPEDITE. LEM |
| 2/12/18 PASSED BY FIRE RETURNED TO C02.PML |
| 2/12/18 STEPHEN DROPPED OFF NEW PERMIT APPLICATION |
| TO REFLECT THE CORRECT ADDRESS; I UPDATED |
| COMMUNITY PLUS WITH NEW ADDRESS RES |
| 2/5/18 STEVEN RESUB TO ADDRESS DENIED COMMENTS SL |
| 9/7/17 DENIED PLANS IN "M" LARGE DRAWER. JPR |
| 8/15/17 PLANS ARE NOT IN CUBICLE C-3. IMPACT FEE |
| PLAN AT J. W. DESK. JW |
| 8/15/17 IMPACT FEES GIVEN TO JWITMER. CP |
| 8/11/17 RESUB OF IMPACT FEES GD |
| 8/10/17 CHANGE OF CONTRACTOR FORM SUBMITTED GD |
| 6/15/17 PLUMB APPROVED RETURN TO C03/GPJ |
| 5/25/17 PASSED BY FIRE RETURNED TO C03.PML |
| 5/19/17 RESUB ADDRESSING DENIED COMMENTS NATALEE |
| 5/17/17 NOTIFIED APPLICANT THAT APPARENT RE-SUB |
| SHEETS ARE ON MY SIDE TABLE BUT THEY NEED TO |
| SUPPLY FORM AND INSERT SHEETS. SAK |
| 4/25/27 IN LARGE DENIED H CONT CUST/GPJ |
| 3/28/17 PASSED BY FIRE, RETURNED TO C02.PML |
| 3/23/17 JOSHUA RESUB TO ADDRESS DENIED COMMENTS |
| SHOLDER |
| 1/24/17 PLUMB DENIED RETURN TO CO5/ GPJ |
| 1/9/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
| C05.PML |