| Miscellaneous Information / Notes |
| INTERIOR BUILD OUT EXTERIOR IMPROVEMENTS INTERIOR |
| EQUIPMENT PREPARATION **FIRE SPRINKLERS REQUIRED** |
| |
| |
| |
| |
| |
| |
| 12/19/17 JORGE PICKED UP CO ORIGINAL RES |
| 4/03/17 JORGE P/U PERMIT SPALMER |
| 3/31/17 READY IN LARGE M/EMAILED OCNTR/CC |
| 3/29/17 PLUMB APPROVED RETURN TO C39/GPJ |
| 3/29/17 ACCEPTED A MID-CYCLE RE-SUB TO ALLOW FOR |
| AN ADDITIONAL MECHANICAL REVIEW IN THIS REVIEW |
| CYCLE. TWO VERSIONS OF SHHET C-1 TO REMAIN IN PLAN |
| SET TO CLARIFY DRAWING INDEX. SAK |
| 3/20/17 PASSED BY FIRE, RETURNED TO C39.PML |
| 3/16/17 RESUB ADDRESSING DENIED COMMENTS NO FEES |
| GD |
| 3/7/17 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
| RESUBMIT, FILED UNDER LARGE DENIED "M". CP |
| 3/7/17 PLUMB DENIED RETURN TO C03/GPJ |
| 2/23/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
| C04.PML |
| 2/14/17 JORGE RESUB TO ADDRESS DENIED COMMENTS |
| SHOLDER |
| 2/6/17 DENIED ON TOP OF FILE CABINET CONT CUST GPJ |
| 1/23/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
| C04.PML |
| 1/19/17 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| SPALMER |
| 12/27/16 JORGE SIGNED OUT 1 SET OF PLANS FOR |
| IMPACT FEES SPALMER. |
| 12/21/16 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
| RESUBMIT, FILED UNDER LARGE DENIED "M". CP |
| 12/19/16 PLUMB DENIED SENT TO ZONE BY GPJ |
| 12/13/16 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
| C08.PML |
| 12/2/16 REQUEST FOR EXPEDITE. SHOLDER |