| Miscellaneous Information / Notes |
| RENOVATION OF A ONE STORY HABITAT STRUCTURE FOR |
| THE WHITE ALLIGATOR |
| |
| |
| |
| |
| 12/16/2016 POSEY PICK UP CO SHOLDER |
| 12/15/2016 CHANGE STATUS FROM OPEN TO CLOSE. FINAL |
| PASSED ON 12/15/2016 BY STEVE PENTEK. MM |
| 10/28/16 JEFF P/U TCO. RB |
| 10/26/2016 ROUTED TO ROBERT BROWN SHOLDER |
| 5/24/16 JEFF P/U PERMIT NSD |
| 5/24/16 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
| FILED UNDER LARGE "G". CP |
| 5/24/16 PASSED BY 'Z', GIVEN TO LMARCHANT FOR |
| FURTHER PROCESSING. JPR |
| 5/20/16 - PLBG. APPROVED/RETURNED TO BIN C22.TKL. |
| 5/19/16 PASSED BY FIRE, FORWARDED TO BUILDING.PML |
| 5/13/16 RESUB ADDRESSING DENIED COMMENTS MS |
| |
| 4/14/16 - DENIED/CONTACTED CONTR./PLACED IN LARGE |
| DENIED UNDER "G".TKL. |
| 3/25/16 RESUB ADDRESSING COMMENTS ASM |
| 3/14/16 FAILED BY 'Z', EMAILED CONTR., FILED IN |
| "G" LARGE DENIED. JPR |
| 2/26/16 PASSED ELECTRICAL REVIEW. RETURNED FILE TO |
| BIN ?C22? FOR ZONING REVIEW. MA |
| 2/2/16 RESUB ADDRESSING DENIED COMMENTS |
| |
| 2/2/16 SUBMITTED CHANGE OF CONTRACTOR FOR ROUTED |
| W/ PLANS MS |
| |
| 11/19/15 FAILED ELECTRICAL REVIEW. CONTRACTOR |
| NOTIFIED VIA EMAIL. SENT TO LARGE DENIED BIN "C". |
| MA |