| Miscellaneous Information / Notes |
| INSTALLATION OF 2- INSULATED HVHZ WINDOWS & 2 |
| -INSULATED HVHZ DOORS |
| |
| |
| |
| |
| 11/17/15 PETER P/U PERMIT SPALMER |
| 11/10/15 EMAILED CONTRACTOR TO INFORM THAT PERMIT |
| IS READY FOR ISSUANCE PENDING PAYMENT OF FEES DUE, |
| UPDATE OF CONTRACTOR LICENSE IF APPLICABLE, AND |
| OWNER?S NOTARIZED SIGNATURE ON APPLICATION IF |
| APPLICABLE. 1 CONTRACTOR SET AND OUR FILE SET ARE |
| FILED IN LARGE PLANS UNDER "A"SH |
| 11/3/15 RESUBMIT ADDIND SPECIAL ENGINEERING, MS |
| |
| 10/09/15 EMAILED CONTRACTOR TO INFORM THAT PERMIT |
| IS READY FOR ISSUANCE PENDING PAYMENT OF FEES DUE, |
| UPDATE OF CONTRACTOR LICENSE IF APPLICABLE, AND |
| OWNER?S NOTARIZED SIGNATURE ON APPLICATION IF |
| APPLICABLE. 1 CONTRACTOR SET AND OUR FILE SET ARE |
| FILED IN LARGE PLANS UNDER "A"SH |
| 10/8/15 ON SH DESK AND OK TO TAKE FOR ISSUANCE SH |
| 10/2/15 RETURNED FROM PAYING IMPACT FEES SPALMER |
| 9/30/15 TOBY SIGNED OUT 1 SET OF PLANS TO TAKE TO |
| IMPACT SPALMER |
| 9/30/15 APPLICATION IN DENIED SMALL "A" SPALMER |
| 9/4/15 RESUB ADDRESSING DENIED COMMENTS ASM |
| 08/25/15 APPLICATION DENIED, EMAILED APPLICANT, |
| FILED SMALL DENIED BIN "A"SH |