| Miscellaneous Information / Notes |
| CONSTRUCT NEW MULTI STORY PARKING GARAGE (EIGHT |
| STORIES INCLUDING ROOFTOP PARKING, BASEMENT) |
| |
| |
| |
| 4/3/19 CERTIFICATE REQUEST TO MELISSA. SAK |
| 6/29/17 CBAA REQUEST ROUTED TO RBOWNS DESK GD |
| 3/21/17 TCO LETTER SUBMITTED ROUTED TO RBROWNS |
| DESK GD |
| 2/13/17 REQUEST FOR TCO HAND DELIVERED TO ROBERT |
| BROWN & SCANNED TO THIS PERMIT SPALMER |
| 1/26/17 CHARLOTTE SUBMITTED REQUEST FOR A TEMP CO |
| ROUTED TO DOUG HARVEY SHOLDER |
| 3/23/16 SUBMITTAL SUBMITTED, NUMBER GENERATED. LWL |
| 3/2/16 "PROTECTIVE CANOPY DRAWINGS" WILL BE |
| SUBMITTED BY CONTRACTOR - THIS IS TO BE TREATED AS |
| A SUBMITTAL (NO FEE, NEW NUMBER GENERATED, |
| SUBMITTAL PERMIT TYPE, ROUTE TO INCOMING) SH |
| 11/24/15 CUSTOMER P/U PERMIT SPALMER |
| 11/24/15 READY, IN LARGE W, TWO SETS GO TO |
| CONTRACTOR, THE RECORD SET IS IN S HILL CUBICLE. |
| SH TO REVIEW THEN SEND TO RECORDS. SAK |
| 11/20/15 RECEIVED CONTRACTS FROM COUNTY; ADJUSTED |
| VALUE; VALUE INCLUDES ROOFTOP CANOPY (STRUCTURAL |
| SUBMITTAL TO BE SUBMITTED PRIOR TO INSTALLATION), |
| EXCLUDES $2M CONTINGENCY SH |
| 11/18/15 ELECTRICAL PASSED. RETURNED TO C28 FOR |
| ENGINEERING REVIEW., MA |
| 11/2/15 MECH PASSED/RETURNED TO C28/CC |
| 10/31/15 ADJUSTED VALUE PER MARSHALL & SWIFT, |
| CALCULATOR METHOD ($47,343,063 LESS $2,091,030 |
| PERMITS ISSUED= $45,343,033), ADVISED APPLICANT |
| VIA EMAIL SH |
| 10/30/15 PASSED BY FIRE, RETURNED TO C28.PML |
| **OK FOR CONTRACTOR TO REPLACE SHEETS S1A THROUGH |
| S6D MID REVIEW** IN BIN C28-C29 SH |
| |
| |
| 10/26/15 ROUTED CALCULATIONS & OPEN PARKING GARAGE |
| CLASSIFICATION BACKUP DOCS TO RECORDS, ADJUSTED |
| VALUE PER COST BREAKDOWN AND ADDED HOLDS FOR |
| IRRIGATION, LANDSCAPING, FENCING PERMITS (VALUES |
| ARE $44,629; $277,377; $30,841) SH |
| 10/21/15 RESUB ADDRESSING DENIED COMMENTS NO FEE. |
| LWL |
| 10/21/2015 RESUB ADDRSSING DENIED COMMENTS NO FEE |
| NSD |
| 10/20/15 ONE SET OF PLANS SIGNED OUT BY LAUREN. |
| LWL |
| |
| 10/1/15 FAILED ELECTRICAL REVIEW. MISSING EXIT |
| LIGHTS ON ROOF LEVEL. CONTACTED FERNANDO DELDAGO. |
| RETURNED TO BIN "C35". MA |
| 9/22/15 PASSED BY FIRE, RETURNED TO C35.PML |
| 09/16/2015 LAUREN RETURNED 3RD SET OF PLANS ROUTED |
| TO SAK ~NSD |
| 09/11/15 RESUB ADDRESSING DENIED COMMENTS ASM |
| 9/10/15 2 OF 3 SETS CHECKED OUT BY LAUREN. SAK |
| 8/31/15 - FAILED ELECTRICAL REVIEW. CONTRACTOR |
| NOTIFIED VIA EMAIL. FILED ON TOP OF DENIED DRAWER |
| CABINET & LARGE BIN LABELED "15060144", 3 ROLLS + |
| SPEC BOOK. MA |
| 6/24/15 MECH DENIED/RETURNED TO C25/CC |
| 6/22/15 PASSED BY ENG. RETURNED TO C25. KEC |
| 6/10/15 FAILED BY FIRE PREVENTION WITH COMMENTS, |
| RETURNED TO C25.PML |