| Miscellaneous Information / Notes |
| 90-INSTALL 132FT OF 2" PVC CONDUIT BY MISSEL BORE |
| AND CONNECT TO ER BRADLEYS. BORE PIT REPAIR TO BE |
| FULL ALLEY WIDTH. #5E843080N |
| |
| CONTRACTOR: AT&T, ERIC DECESARE, 561-357-6509 |
| SUB: IVY SMITH, ORTON TRENT, 954-351-3114 |
| START DATE: 06-11-2015 |
| DURATION: 90 DAYS |
| END DATE: 09-09-2015 |
| BAGGING OF PARKING METERS IS REQUIRED WHEN |
| BLOCKING PARKING STALLS. DO NOT PARK ON THE |
| SIDEWALK. LIGHTED BARRICADES ARE REQUIRED FOR |
| EQUIPMENT OR DUMPSTER (POD) LEFT IN ROADWAY OR |
| PARKING STALL. R/W & S/W RESTORATION PER CURRENT |
| CITY STD. COPY OF BORE LOGS & AS-BUILTS REQUIRED. |
| ALL TYPE I&II BARRICADES TO HAVE SAND BAG BALLASTS |
| OVER BOTTOM RAILS. |
| NO WORK ALLOWED BETWEEN |
| 7:00AM-9:00AM&4:00PM-6:00PM. |
| PLEASE BE SURE TO CALL IN THE FOLLOWING |
| INSPECTIONS (LISTED ON THE BACK OF THE PERMIT): |
| B800,801,802,803,804,805,807 |
| PLEASE BE SURE TO FOLLOW THESE SPECIAL CONDITIONS |
| (LISTED ON THE BACK OF THE PERMIT): |
| A,B,C,D,E,F,G,H,I,J,K,L,M600 |