| Miscellaneous Information / Notes |
| NEW METAL BUILDING WAREHOUSE |
| |
| |
| |
| |
| |
| 9/23/15 FEES PAID TCO PICK UP BY ROSE SEW |
| 9/22/15 TCO APPROVED READY TO ISSUE UPON FEE 500$, |
| MS |
| |
| 9/21/14 TCO REQUEST SUBMITTED SCANNED AND ROUTED |
| TO DH DESK, MS |
| |
| 8/24/15 TCO REQUEST SUBMITTED AND ROUTED TO |
| DHARVEY SEW |
| |
| 7/28/15 ZONING SENT TO JR>SG |
| 05/22/15 P/U BY MARTIN ASM |
| 05/21/2015 CALLED CONTRACTOR, PERMIT IS READY FOR |
| ISSUANCE, FILED UNDER "A" LARGE PLAN. JW |
| |
| 05/20/2015 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| NSD *** ROUTED TO JW*** |
| *******5/19/2015 NEED UPDATES FROM ROSE KENNEY |
| BEFORE PLAN REVIEW CAN BE COMPLETED. JW ******* |
| |
| 5/18/15 PASSED BY FIRE PREVENTION, RETURNED TO |
| C25.PML |
| 5/14/15 RESUB SUBMITTED ADDRESSING DENIED |
| COMMENTS, NO FEE. LWL |
| 5/13/15 PASSED BY 'Z', EMAILED CONTR., FILED UNDER |
| "A" LARGE DENIED PLANS. JPR |
| 4/20/15 FAILED BY FIRE PREVENTION WITH COMMENTS, |
| RETURNED TO C37 |
| 04/16/15 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| ASM |
| 4/2/15 - DENIED/E-MAILED CONTR. /PLACED IN LARGE |
| DENIED UNDER "ABC OVERFLOW".TKL. |
| 3/5/15 PASSED BY ENG. RETURNED TO C25. KC |
| 3/4/15 FAILED BY FIRE PREVENTION WITH COMMENTS, |
| RETURNED TO C25.PML |
| 03/02/2015 RESUB ADDRESSING DENIED COMMENTS, MS |
| |
| 1/15/15 FAILED BY ZONING, EMAILED CONTR., FILED |
| UNDER "A" LARGE DENIED PLANS. JPR |
| 12/15/14 FAILED BY ENG. RETURNED TO C03. KC |
| 12/1/14 FAILED BY FIRE PREVENTION WITH COMMENTS, |
| RETURNED TO C03.PML |