| Miscellaneous Information / Notes |
| PLANET FITNESS - TENANT FIT-OUT OF EXISTING SUITES |
| 19&20, PARTIAL NEW MECH, ELEC & PLUMB WORK |
| |
| |
| 06/3/15 TCO P/U BY SALVATORE ASM |
| 6/3/15 ISSUED TCO. CALLED SAL FOR P/U.KC |
| 5/28/15 TCO REQUEST SUBMITTED.KC |
| 3/13/15 PLANS IN FILENET. CP |
| 3/13/15 PEDDS APPROVED APPLICANT INVITED TO |
| DOWNLOAD PLANS AND PICK UP PERMIT CARD. CP |
| 3/12/15 PEDDS SUBMITTED GIVEN TO SKENNEDY. CP |
| 3/11/15 ATTACHED CONTRACTOR TO APPL. ROUTED TO CP |
| DESK. DID NOT ISSUE PERMIT PEDDS WERE NOT |
| SUBMITTED. MS |
| 3/5/15 IMPACT FEES PASSED, APPLICANT INVITED TO |
| SUBMIT PEDDS, ORIG APPLICATION WITH OWNER SIGN & |
| ATTACH CONTRACTOR TO PROJECT. CP |
| 3/3/15 PUT IMPACT FEE SUBMITTAL IN SMALL S AS IT |
| HAS NO EVIDENCE OF PBC IMPACT FEE REVIEW. |
| APPLICANT ADVISED TO PICK UP THE ENTIRE SUBMITTAL |
| AND RETURN AFTER IMPACT FEE REVIEW IS COMPLETE. |
| SAK |
| 3-3-15 "REVISED COVER SHEET TO ADDRESS IMPACT FEE |
| COMMENT" ROUTED TO C PUELL WL |
| 2/17/15 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 2/17/15 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 1/21/15 RESUB PLANS UPLOADED, INCOMING COMPLETE. |
| CP |
| 1/8/15 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. CP |
| 12/30/14 ZONING APPROVED.SG |
| 11/26/14 FEES PAID, INCOMING COMPLETE. CP |
| 11/25/14 PLANS UPLOADED, WAITING ON FEES & SUITE |
| #. CP |
| 11/24/14 APPLICANT INVITED TO UPLOAD PLANS. EMAIL |
| SENT TO PAY PARTIAL FEES, ONCE FEES PAID, PERMIT |
| FEE OF $8050 WILL BE ADDED. CP |