| Miscellaneous Information / Notes |
| FORMER "WINN DIXIE" DEMO |
| |
| |
| |
| |
| |
| 12/29/2014 PERMIT P/U BY SALVATORE ASM |
| 12/11/14 READY, IN LARGE TBD, NEEDS, FEE, |
| CONTRACTOR,NOC, EMAILED BEN. SAK |
| 12/10/14 SENT TO ENGINEERING, MG. SAK |
| 12-6-14 RECEIVED NEEDED DOCS. STEVE K. KEEPING TO |
| ADD TO ORIGINALS SUBMITTED WHEN OUT OF |
| ENGINEERING. TM |
| |
| 12/3/14 RESUB ADDRESSING COMMENTS NO FEE (WAS SENT |
| VIA FEDEX) ROUTED TO TMOORE SEW |
| 12-3-14 RECEIVED TWO COPIES OF STRUCTURALS FROM |
| BEN BRIDGES. TRYING TO BE CLEAR ON HOW THE |
| DEMISING WALL BETWEEN WINN-DIXIE AND SUBWAY WILL |
| BE DEMOLISHED SAFELY. CALLED BEN BRIDGES AND ASKED |
| FOR A COPY OF THE 5/S102 SECTION THRU THAT WE NEED |
| BUT IS NOT INCLUDED. WILL GET WITH SANDY TO HAVE |
| THESE ENTERED CORECTLY. TM |
| |
| 12-2-14 RECEIVED ASBESTOS ABATEMENT PAPERWORK. |
| KEEPING AT MY DESK UNTIL PLAN RETURNS. TM |
| |
| |
| 11/24/14 FAILED BY FIRE PREVENTION, FORWARDED TO |
| ENGINEERING.PML |
| 11-24-14 JUST SPOKE WITH SAL ON PLAN REVIEW |
| COMENTS LISTED 11-22-14. HE AGREES SEPERATE FIRE |
| LINE PERMIT WILL BE FASTER, WILL BRING US A |
| SHORING DETAIL FOR PHASE 1 LEAVING WALL SHARED |
| WITH SUBWAY, AND DISCUSSED MISSING UTILITIES |
| RELEASES. TM |
| |
| 11-22-14 REVIEWED AND MOVING TO FIRE'S MAILBOX FOR |
| THEIR REVIEW. TM |
| |
| 11/20/14 PERMIT PKG MAILED - NO DEBRIS FORM WAS |
| INCLUDED SEW |