| Miscellaneous Information / Notes |
| NEW CONSTRUCTION 1-STORY DAYCARE CENTER(CBS) |
| MATTISYN SCHOOL |
| |
| |
| |
| |
| |
| 10/24/12 REBUILTS PLANS REVIEWED BY FIRE |
| (APPROVED).(RF)PLANS WAS RE-OPENED AND CLOSED BY |
| FIRE, BECAUSE ENGINEER FORGOT TO INSTALL AN |
| (FDC).PLANS PLACED ON SANDY'S DESK. |
| 10/24/12- 2-COPIES AS-BUIT SURVEY FOR FDC LOCATION |
| PLACED IN FIRE REVIEW BOX.KC |
| 10/19/12-ISSUED CO. CALLED TROY FOR P/U.TO CO BOX, |
| "J".KC |
| 9/4/12- REC'D TRUSS/STRUCTURAL ROOF FRAMING COC |
| LETTER. RELEASED HOLD. |
| 8-14-12 TEMPORARY POWER RELEASE FORM ROUTED TO P |
| PETTY (SCANNED & E-MAILED TO PHIL) WL |
| 6/19/12 STOP WORK ISSUED FOR WORK AT AREAS OF THE |
| MANSARD TRUSS FRAMING. SEE STOP WORK ORDER ON |
| ATTACHMENTS.LEFT MESSAGE WITH CONTRACTOR.KC |
| 3/05/2012 PLANS BACK FROM PBC FOR IMPACT FEE |
| ASSESSMENT FILED UNDER J LARGE PLANS. JW |
| 3/5/12 ONE SET OF PLANS SIGNED OUT FOR IMPACT SEW |
| 3/05/ 12 CALLED CONTRACTOR PLANS ARE READY FOR |
| IMPACT FEE ASSESSMENT, FILED UNDER "J" LARGE PLANS |
| BACK OF HOUSE. JW |
| 3/05/2012 HOLD NEW CORRECTED FLOOD ZONE |
| CERTIFICATE REQUIRED. JW |
| 2/29/12 PUT IN BIN #C28 SH |
| 2/29/12 GIVEN TO LM TO ORGANIZE AND ROUTE - ES |
| 2/22/12 SENT TO ZONING BOX LM |
| 2/21/12 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| SPALMER |
| 02/02/2012 CALLED CONTRACTOR PLANS DENIED & FILED |
| UNDER "J" LARGE PLAN. JW |
| 01/09/2012 1ST RESUBMITTAL JW |
| 12/19/11 CORR, CALLED CONTR, DENIED LARGE BIN |
| 'TBD' SH |
| |
| |
| |
| |
| |
| |
| |