| Miscellaneous Information / Notes |
| INTERIOR RENOVATION TO EXISTING THEATER |
| |
| |
| |
| **DIGITAL PLANS** SEE PROJECTDOX |
| |
| |
| 3/6/12 COC P/U BY MARK FURMAN KM |
| 1/4/12 TCO P/U BY MARK FURMAN KM |
| 1/4/12 CALLED MARK TO P/U 2ND TCO. IN CO BOX UNDER |
| "B". RB |
| 12-30-11 ROUTED 2ND TCO REQUEST TO R BROWN WL |
| 11/8/11 CALLED MARK TO P/U REVISED TCO. IN CO BOX |
| UNDER "B". RB |
| 10/6/11 MARK P/U CO AR |
| 10/5/11 CALLED BILL BRANNING TO PICK UP TCO. IN CO |
| BOX UNDER "B". RB |
| 10/4/11 BILL BRANNING SUBMITTED ONM&J LETTER, |
| CARPET FLAMMABILITY TEST REPORT, AND REAR DOOR |
| NOA. ROUTED TO T MOORE'S DESK. RB |
| 9-20-11 MARK FURMAN SUBMITTED COPY OF NOC SEE |
| NOTES WL |
| 5/13/11 PEDDS SIGNATURE DOCUMENTS RECEIVED. PLANS |
| BATCH-STAMPED AND READY FOR DOWNLOAD. PERMIT |
| PRINTED AND PICKED UP BY CONTRACTOR. RJR |
| 5/9/11 SPOKE TO BILL BRANNING, INFORMED THAT PEDDS |
| SIGNATURE DOCS ARE REQUIRED TO BE SUBMITTED FROM |
| EACH DESIGN PROFESSIONAL PRIOR TO PERMIT ISSUANCE. |
| APPROVED PLANS MAY BE DOWNLOADED FROM PROJECTDOX |
| ONCE PERMIT IS ISSUED. RJR |
| 4/7/11 1ST ROUND REVERS COMPLETE. A RESUBMIT IS |
| REQUIRED TO ADDRESS PLAN REVIEW COMMENTS. |
| APPLICANT HAS BEEN NOTIFIED VIA EMAIL. RJR |
| 3/15/11 PERMIT PACKAGE FILED IN SCAN ROOM-PERMIT |
| PACKAGE WILL BE SCANNED ONCE STATUS IS UPDATED TSJ |
| 3/4/11 ROUTED APPLICATION TO REGUEIRO SEW |