| Miscellaneous Information / Notes |
| BLDG 3 INTERIOR BUILDOUT FRAMING INSULATION |
| DRYWALL FLOORING PLUMBING FIRE SPRINK HVAC ELEC |
| |
| |
| |
| **ELECTRONIC PLANS** SEE PROJECTDOX |
| |
| 11/19/10 STEVE P/U PERMIT SPALMER |
| 11/17/10 VALUE ADJUSTED. VALUES OF STAND-ALONE |
| PERMITS HAVE BEEN DEDUCTED FROM MASTER PER |
| ATTACHED SPREADSHEET PROVIDED BY STEVE PROVINES OF |
| CATALFUMO CONSTRUCTION. ANY PERMITS APPLIED FOR |
| RELATED TO THIS PROJECT SHALL BE VALUED BASED ON |
| THE SPREADSHEET. RJR |
| 11/17/10 PER DW, SEPARATE SITE LIGHTING PERMIT |
| REQUIRED. VALUE FOR THIS SUB-PERMIT SHALL BE $0 AS |
| VALUE IS ALREADY INCLUDED IN THE MASTER PERMIT. |
| RJR |
| 10/20/10 PRESCREEN PASSED. REVIEWS ASSIGNED. RJR |
| 10/19/10 FIRST RESUB UPLOADED. RJR |
| 10/14/10 FIRST REVIEW CYCLE COMPLETE. APPLICANT |
| NOTIFIED VIA EMAIL. COMMENTS AND DRAWING MARK-UPS |
| AVAILABLE ONLINE. RJR |
| 10/05/2010 ENG REVIEW FAILED [email protected] |
| 8/25/10 PLANS FOR 3 BUILDINGS SUBMITTED TOGETHER. |
| BUILDING 1 IS UNDER PERMIT # 10080589. BUILDING 2 |
| IS UNDER PERMIT # 10080594. BUILDING 3 IS UNDER |
| PERMIT #10080599. ALL REVIEWS FOR THESE THREE |
| PERMITS ARE BEING PERFORMED UNDER BUILDING 1 |
| #10080589. ALL THREE PERMITS WILL BE ISSUED |
| SIMULTANIOUSLY WHEN COMPLETE. RJR |