| Miscellaneous Information / Notes |
| ALTER & REPAIRS DRYWALL/NEW DOORS/STUCCO/STOOP |
| PAVERS/CONCRETE REPAIRS PLUMB/ELEC |
| |
| |
| |
| |
| 12/1/11 CALLED PETER TO P/U CERTIFICATE OF |
| COMPLETION. IN CO BOX UNDER "P". RB |
| 5/20/11 CHANGE OF CONTRACTOR $100 SMH |
| 5/2/11 CONTRACTOR P/U PERMIT AR |
| 4/22/11 CALLED CONTRACTOR PLANS READY TO ISSUE, |
| OWES FEES, FILED UNDER "C" LARGE PLAN. JW |
| 4/20/11 ROUTED TO RAK. LMF |
| 4/20/11 PLANNING AND ZONING: **** PASSED WITH |
| PROVISO: THIS PERMIT IS FOR INTERIOR WORK ONLY. |
| SEPARATE PERMITS ARE REQUIRED FOR ALL EXTERIOR |
| WORK (FOR EXAMPLE, PARKING STRIPPING, DUMPSTER |
| ENCLOSURE) PRIOR TO C.O. OR CERTIFICATE OF |
| COMPLETION C.O.C. ANY OTHER WORK SUCH AS SIGNAGE, |
| MURAL WORK REQUIRES ADDITIONAL PERMITS PRIOR TO |
| WORK BEING PERFORMED (WHEN THE APPLICANT IS READY |
| TO SUBMIT). LMF |
| |
| THE PROPOSED PARKING IS BACKING INTO ADJACENT |
| PROPERTY, WHICH IS NOT ALLOWED PER ZLDR, SECTION |
| 94-485(N). IS THERE AN EXISTING RECORDED ACCESS |
| AGREEMENT WITH THE ADJACENT PROPERTY OWNER? |
| |
| RE-SUBMITTAL: A RECORDED ACCESS AGREEMENT IS |
| REQUIRED, PRIOR TO THE APPROVAL BY THE PLANNING |
| AND ZONING DEPARTMENT. |
| |
| 3/3/11 EMAIL NOTE TO PROPERTY OWNER: THE CURRENT |
| RECORDED COPY FOR THE EASEMENT THAT IS SET TO |
| EXPIRE IN TWO (2) YEARS OR EARLIER WITH A 90-DAY |
| NOTICE, THEN WE WILL APPROVE THE PERMIT WITH THE |
| CONDITION THAT IF THE ACCESS EASEMENT AGREEMENT |
| EVER EXPIRES OR IS NULLIFIED, THEN THE LAND WILL |
| NO LONGER HAVE LEGAL ACCESS FROM 25TH STREET. |
| THEREFORE, ACCESS WILL HAVE TO BE PROVIDED FROM |
| THE ALLEY TO YOUR PROPERTY. SINCE YOU HAVE ONLY |
| ABOUT 20+' OF ACCESS FROM THE ALLEY THAT IS |
| CURRENTLY PROPOSED TO HAVE A DUMPSTER ENCLOSURE |
| AND PARKING SPACES, THEY WILL ALL HAVE TO BE |
| REMOVED SO THAT ADEQUATE ACCESS TO YOUR PROPERTY |
| IS MAINTAINED. OTHER ARRANGEMENTS WILL HAVE TO BE |
| MADE TO PROVIDE A DUMPSTER ENCLOSURE ON THE |
| PROPERTY THAT IS ACCEPTABLE TO THE CITY AT THAT |
| TIME. |
| |
| 4/18/11 PASSED WITH PROVISO: SEPARATE PERMIT |
| APPLICATION, PLANS AND FEES ARE REQUIRED FOR |
| DUMPSTER ENCLOSURE, PARKING, STRIPING, ASPHALT. TO |
| BE COMPLETED PRIOR TO C.O. (CERTIFICATE OF |
| OCCUPANCY) M GONZALEZ (ENGINEERING) |
| |
| 4/15/11 CLARAROSE REMOVED PLANS FOR EXTERIOR WORK |
| AND RESUBMITTED PLANS FOR PERMIT ISSUANCE. RB |
| 4/15/11 CLARAROSE WAS CALLED AND ASKED TO REMOVE |
| THE EXTERIOR WORK FROM THE SCOPE OF THIS PERMIT. |
| SO VALUE OF WORK IS BEING REDUCED FROM $142,000 TO |
| $122,000. SEPARATE PERMIT APPLICATIONS WILL BE |
| SUBMITTED FOR THE PARKING LOT, DUMPSTER ENCLOSURE, |
| LANDSCAPING, ETC. RB |
| 3/31 RROD-SCHEDULED MEETING FOR NEXT THURS 4/7 TO |
| SPLIT PERMIT. LMF |
| 3/2 CONTACTED OWNER/ARCHITECT TO SPLIT PERMIT |
| (INTERIOR VS. EXTERIOR WORK) SO HE CAN START ON |
| THE INTERIOR WORK. |
| 2/14/11 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| SEW |
| 1/12/2011 DENIED PLANS FILED UNDER "C" LARGE PLAN |
| JW |
| 01-12-2011 TO JIM WITMER |
| 10-13-10 1ST RESUB "ADDRESSING CORRECTIONS" WL |
| 8/10/10 PLANS DENIED CALLED LEFT A MESSAGE WITH |
| THE CONTRACTOR. PLANS IN BACK IN BIG BEN (C) HM. |
| 8/6/10 FAILED "L" * RETURNED TO C-26 ---RAK |
| 8/5/10 ROUTED TO RAK. LMF |
| |
| |
| |
| |
| |