| Miscellaneous Information / Notes |
| FOUNDATION & FIRST LIFT OF COLUMNS |
| PROJECT:08120552 |
| |
| |
| |
| |
| |
| |
| 10/25/10 FEES PAID LETTER PU BY JOE SEW |
| 10/20/10 CALLED JOE TO P/U LETTER EXTENDING PERMIT |
| TO 3/7/2013 PER SENATE BILL 1752. "M". RB |
| 10/20/10 JOE SULLIVAN EMAILED A COPY OF A LETTER |
| DATED 9/14/10 REQUESTING THAT THE PERMIT BE |
| EXTENDED TO 3/7/12 PER SENATE BILL 1752. RB |
| 6/15/10 PERMIT EXTENSION $50 SPALMER |
| 6/15/10 APPLICATION EXTENDED TO 9/14 DRF |
| 3/9/2010 APPLICATION EXTENDED FROM 3/18 TO 6/16 |
| DRF |
| 3/9/2010 RECVD LETTER REQUESTING EXTENSION TO APP |
| - DRF |
| 12/21/2009 RCVD LETTER TO REQUEST FOR AN EXTENSION |
| FEES $50.00 SEE NOTES BELOW FROM RB ROUTED TO |
| DIANE FULCHER'S DESK MMILLER |
| 12/21/09 JOE SULLIVAN CALLED TO ADVISE THAT HE IS |
| BRINGING IN THE $50 PERMIT EXTENSION FEE PLUS A |
| LETTER TO REQUEST EXTENSION FOR THIS PERMIT. RB |
| 10-02-09 1 SET OF FOUNDATION PLANS PLACED IN |
| DENIED CABINETS FILED UNDER "M" LARGE PLANS JW |
| 6-23-09 JOE SULLIVAN HAS TAKEN (2) SETS OF PLANS/ |
| PERMIT APP TO P B C IMPACT FEE OFFICE FOR |
| ASSESSMENT |
| JW HAS (1) SET AT DESK. |
| 6-18-09 J. WITMER PLANS ARE STAMPED AT MY DESK |
| AWAITING FOR PICK UP FOR IMPACT FEE ASSESSMENT. |
| 6/16/09 TALKED WITH ARCHITECT MIKE DUMULA AND HE |
| WILL COME IN TO SIGN/SEAL THE ARCHITECTURAL PLANS |
| THAT ARE IN COMMERCIAL BOARD SLOT C4 TO ADDRESS |
| ZONING'S COMMENT.RB |
| 06/02/2009 1ST RESUB PLANS PLUS APP NO FEE MMILLER |
| 3-17-09 JOE SULLIVAN PICKUP PLANS WL |
| 3-09-09 CALLED CONTRACTOR PLANS FILED UNDER "M" |
| LARGE PLANS JW |
| 2-23-09 3 SETS OF PLANS (ONE ROLL).PLS CHG OWNER |
| INFO BEFORE ISSUING PERMIT, OWNER INFO WILL CHG |
| ONCE UNITY OF TITLE IS DONE WITH PROPERTY |
| APPRAISER (NEW OWNER WILL BE "WEST PALM BEACH |
| HOTEL GRUP LLC". PER PROJECT #08120552, ADDRESSING |
| IS USING PARCEL #74434321080550040, (SEE PROJECT |
| ADDRESSING COMMENTS) CONTR PD 30% $5412.00 WL |