| Miscellaneous Information / Notes |
| INSTALL CLEAR STORM PANELS ON 11 WINDOWS 1 DOOR |
| AND 2 GABLE VENTS ALUMINUM STORM PANELS ON ENTRY |
| |
| |
| |
| 12/08/2008 APPROVED SUMBITTAL THAT WAS SUBMITTED |
| ON 12/05/2008 WAS P/U BY CHRIS MMILLER |
| 12-8-08 TALKED TO MARK. BLDG SUBMITTAL UNDER "B". |
| JG. |
| 12/05/2008 BLDG SUBMITTAL NO FEE (ROUTED TO JULIO |
| GOMEZ'S DESK)ACCORDING TO CUSTOMER DID CHARGE |
| CUSTOMER REVISION BECAUSE HE STATED TO ME (MIRELLE |
| MILLER) THAT HE TOLD BY PLANS EXAMINER HE WAS NOT |
| GOING TO BE CHARGED A FEE MMILLER |
| 12-01-08 TALKED TO MARK. HE'LL BRING ENGINEER'S |
| REVISION LETTER FOR MIN. SIZE PANEL. JG. |
| 11/236/2008 PERMIT PLUS PLANS P/U BY CHRIS MMILLER |
| 11-20-08 LEFT MESSAGE ON CONTRACTOR'S VOICE MAIL. |
| PERMIT UNDER "B". JG. |
| 11-20-08 MARK (CONTRACTOR) FAXED REVISED |
| INSTALLATION SCHEDULE. JG. |
| 11-13-08 TALKED TO MARK TO GO OVER COMMENTS. JG. |
| 11-12-08 FAXED COMMENTS TO MARK. JG. |
| 11/12/08 NOC FAXED AND UPDATED PUT W/PERMIT PKG ON |
| JGOMEZ DESK SEW |
| 11-6-08 LEFT MESSAGE ON CONTRACTOR'S VOICE MAIL. |
| PLANS ON JULIO'S DESK. WAITING FOR CONTRACTOR TO |
| CALL BACK. JG. |
| 11/5/08 NOC FAXED AND UPDATED ROUTED TO PERMIT PKG |
| SEW |