| Miscellaneous Information / Notes |
| CONSTRUCT GUEST SUITE ADDITION |
| |
| |
| |
| |
| |
| 2-24-09 KIM LIDDELL PICKUP PLUMB REV (DATED |
| 1-29-09) WL |
| 2-23-09 CALLED FOR P/U OF PLMG REVISION AND LEFT A |
| MSG ON KIM L'S VOICE MAIL INDICATING THE |
| REQUIRMENT FOR THE RECIEPT OR BLUE CARD. "T" |
| KSTEVENS. |
| 1/29/09 PLUMBING REV RISER $80 SEW |
| 1/27/09 KIM P/U MECH REV DATED 1/13/09 SPALMER |
| 01/26/2009 CALLED CUSTOMER APPROVED MECHANICAL |
| REVISION THAT WAS SUBMITTED ON 01/13/2009 IS READY |
| FOR P/U FILED UNDER "T" MMILLER |
| 1/13/09 MECH REV $80 SPALMER |
| 1/13/09 KIM P/U REV DATED 12/3/08 SPALMER |
| 01-13-09 CALLED FOR P/U PLMG REVISION AND LEFT A |
| MSG ON KIM L'S VOICE MAIL INDICATING THE REVISION |
| WAS DENIED AND THE BLUE CARD OR RECIEPT WAS REQD. |
| "T" KSTEVENS. |
| 12/03/2008 PLUMBING REVISION # 01 FEES |
| 11/25/08 NOC FAXED AND UPDATED INPSECTION HOLD |
| RELEASED SEW |
| 10/27/08 LEFT MESSAGE /OWES FEES/NEEDS |
| NOC/UNDER'T' BIG PLAN BIN RM |
| 10/02/08 1ST RESUB NO FEE SPALMER |
| 9/18/08 KIM P/U DENIED PLANS SPALMER |
| 9/17/08 DENIED/CALLED/OWES FEES/UNDER 'T'BIG BIN |
| RM |
| 9/7/08 - ZONING FAILED. SENT TO INCOMING FOR |
| FURTHER PROCESSING. ~MC |