| Miscellaneous Information / Notes |
| INTERIOR BUILDOUT PHASE IV |
| |
| |
| |
| |
| 03/26/2009 APPROVED BLDG APPROVED ELECTICAL |
| APPROVED MECHANICAL & APPROVED FIRE THAT WAS |
| SUBMITTED ON 03/24/2009 WAS P/U BY ROSE MMILLER |
| 03/26/2009 CALLED CUSTOMER READY FOR P/U FILED |
| UNDER "A" DVP |
| 3/24/09 EXPEDITED REQUEST: SPOKE TO ROSE, GAVE |
| ESTIMATED FEES AND COMPLETION DATE. FEES ADDED TO |
| PERMIT (8 HOURS). RJR |
| 3/24/09 EXPEDITED PLAN REVIEW REQUEST ROUTED TO |
| RREGUEIRO SEW |
| 3/24/09 BLDG/ELEC/MECH/FIRE REV PER ATTACHED PLANS |
| SEW |
| 1/6/09 CHANGE OF CONTRACTOR $100 SPALMER |
| 06/13/2008 RCVD NOC PERMIT PLUS PLANS P/U BY TANYA |
| STYLES MMILLER |
| 06/09/2008 CALLED CUSOTMER NEEDS NOC CALLED |
| CUSTOMER PERMIT PLUS PLANS READY FOR P/U FILED |
| UNDER LARGE BINS "H" MMILLER |
| 6/6/8 PLANS SENT TO PROCESSING SMH |
| 5/29/08 2ND RESUB $ SPALMER |
| 5-21-08 JOHN BANTING PICKUP DENIED PLANS WL |
| 05/19/08 CALLED FOR PLANS P/U; IN LARGE BIN "H" |
| MAW |
| 04/30/08 1ST RESUB NO FEE SPALMER |
| 03-24-08 DAISY PERRY PICKUP DENIED PLANS WL |
| 03/24/08 CALL FOR P/U, W/CORR'S, UNDER(H), LEFT VM |
| MESSAGE FOR DAISY PERRY, **LARGE BINNS** |
| ADARROUGH |
| 02/11/08 NO SUBS SIGNED ON AT TIME OF APPLICATION |
| SUBS WILL PULL THEIR OWN PERMITS SPALMER |