| Miscellaneous Information / Notes |
| CONSTRUCTION OF AN 11,900 SF MAINTENANCE FACILITY |
| |
| |
| |
| |
| |
| 10-6-09 KURT KING PICKUP REV (DATED 9-29-09) WL |
| 10/6/09 PLANS UNDER "W" ( SMALL)FOR PU. CALLED AND |
| LEFT A MESSAGE FOR KURT. REMINDED OF BLUE CARD. DV |
| PALMER. |
| 10/5/09 GAVE TO DEWEY LM |
| 10/5/09 SENT TO LM FOR PROCESSING BY ES |
| 9/29/09 ZONING/LANDSCAPING $170 SPALMER |
| 9/22/09 REVISIONS FROM 7/22 FILED UNDER 'W' LM |
| 8/12/09 ELEC REV PU BY ROBERT SEW |
| 8/12/09 (2) PLUMBING REV DATED 7/20 & 7/27 PU BY |
| ROBERT SEW |
| 8/7/09 ELEC REV UNDER "W" FOR PU. CALLED AND LEFT |
| MESSAGE ON JENNIFER'S CELL. REMINDED OF BLUE CARD. |
| DV PALMER. |
| 7-20-09 CALLED FOR P/U OF PLMG REVISION AND LEFT A |
| MSG ON JENNIFER S'S VOICE MAIL INDICATING THE |
| REQUIREMENT FOR THE RECIEPT OR BLUE CARD. "W" |
| KSTEVENS. |
| 7-27-09 REV #8 $80 PLUMBING "RESPONDING TO |
| COMMENTS FROM PLUMBING PLAN REVIEWER" WL |
| 7/22/09 REV RELOCATE HANDICAP STALLS $230 SPALMER |
| 7-22-09 CALLED FOR P/U OF APPROVED PLUMBING |
| REVISION AND TO INDICATE ONE SHEET WAS DENIED. |
| SPOKE TO JENNIFER S. INDICATING THE REQUIREMENT |
| FOR THE BLUE CARD OR RECIEPT. "W" KSTEVENS. |
| 7/20/09 PLUMBING REV ADDRESSING DENIED COMMENTS |
| FROM REV DATED 6/19/09 $110 SEW |
| 7/20/09 REV DATED 6/19/09 PU BY JENNIFER |
| 7/20/09 MECH REVISION AND PRODUCT APPROVALS CALLED |
| FOR P/U. LEFT MSG FOR JENNIFER. SM BIN UNDER "W". |
| PLUMBING REVISION WAS DENIED AND RETAINED, IN |
| SMALL FILE UNDER "W" RJR |
| 7/20/09 REV PU DATED 7/15/09 PU BY JENNIFER |
| 7-20-09 CALLED CONTRACTOR REVISIONS ARE FILED |
| UNDER "W" SMALL PLANS JW |
| 7/15/09 BLDG REV STRUCTURAL RELATING TO THE |
| STRUCTURAL STEEL ANGLES PLATES & HSS (TUBE STEEL) |
| SEW |
| 07/13/2009 ELECTRICAL REVISION #04 FEES $140.00 |
| MMILLER |
| 6/19/09 BLDG/PLUMBING/MECH REV CHANGES TO HVAC |
| DUCT LAYOUT & PRODUCT APPROVAL FOR DOORS & LOUVERS |
| $ SEW |
| 5/27/09 ELEC REVISION PICKED UP BY JENNIFER |
| SUBMITTED ON 5/5. NO REVIEW DONE. WILL HAVE A $110 |
| CREDIT. DV PALMER. |
| 5-5-09 REV #2 ELEC $110 "APPROVAL FOR PAD MOUNT |
| GENERATOR CONNECTION CABINET" WL |
| 2-12-09 DANIELLE GANCI PICKUP ELEC REV (DATED |
| 1-23-09) WL |
| 2/10/09 ELEC REV FROM 1/23 OK UNDER "W" (SMALL) |
| FOR PICK UP. CALLED AND LEFT MESSAGE ON CELL VM |
| FOR JENNIFER. REMINDED OF BLUE CARD. DV PALMER. |
| 01/23/2009 ELECTRICAL REVISION #01 FEES $110.00 |
| MMILLER |
| 12-5-08 KEVIN P/U PERMIT MJACOBS. |
| 12-5-08 CALL TO P/U PERMIT UNDER 'W' MJACOBS |
| 12/04/08 PLANS READY FOR PROCESSING & PERMIT |
| ISSUANCE ONCE CONTRACTOR SUBMITS (1)SHEET OF FP-2 |
| FOR FIRE STAMPING; FILED IN BOTTOM LARGE BIN "W" |
| MAW/FIRE |
| 11/24/08 SUBMITTAL BROUGHT IN BY AMY. DV PALMER. |
| 11-6-08 2ND RESUB $1878.00 "PLS SEE ALL MATERIALS |
| INCLUDED ALSO INCLUDED ARE ALL COMMENTS"...PLANS |
| ARE IN BOX WITH PINK PKG WL |
| 9-24-08 DANIELLE GANCI PICKUP DENIED PLANS WL |
| 09/22/08 CALLED FOR PLANS P/U; IN BOTTOM BIN "W" |
| MAW |
| 08/20/08 1ST RESUB PLANS PLUS APP NO FEE |
| MMILLER |
| 06/26/08 DANIELLE P/U DENIED PLANS SPALMER 0 |
| 6/24/08 CALLED FOR PLANS P/U; IN LARGE BIN "W" |
| MAW |
| 06/13/08 CHANGED PERMIT APPLICATION DATE TO |
| 5/12/08 AS THE PERMIT WAS NOT APPLIED WITH A |
| CONTRACTOR UNTIL THIS DATE. THE PLANS WERE |
| SUBMITTED ONLY FOR "PLAN REVIEW" PREVIOUSLY. DV |
| PALMER. |
| 05/12/08 SUBMITTED AS PERMIT SLS |
| 12-27-07 FRANCIS SIRLEAF PICKUP PLANS WL |
| 12-1-07 CALLED FOR P/U AND TALKED TO FRANCIS AND |
| TOLD HIM THERE WERE COMMENTS TO BE ADDRESSED AND |
| TO BRING HIS RECIEPT OR BLUE CARD TO RETRIEVE THE |
| PLANS. "R-LARGE" KSTEVENS |