| Miscellaneous Information / Notes |
| DEMO MAJORITY OF EXISTING STRUCTURE LEAVE (2) |
| WALLS & SLAB REPLACE W/ADDITION OF CBS & SLAB |
| |
| |
| |
| |
| |
| 1/27/09 PLBG REVISION P/U BY NICK SLS |
| 1/23/09 REV. OK. CALLED NICK FOR P/U UNDER "B" |
| SMALL LEW 3592 |
| 1/22/09 PLUMBING REV $80 SEWER LINE IN REAR OF |
| PROPERTY ORIGINAL DRAWING SHOWN IN FRONT SEW |
| 1/15/09 PU BY NICK SEW |
| 1/13/09 PLBG. REV. DENIED. CALLED MIKE M. FOR P/U |
| UNDER "B" SMALL. LEW 3592 |
| 01/08/2009 APPROVED ELECTRICAL REVISION THAT WAS |
| SUBMITTTED ON 12/19/2008 WAS P/U BY NICK MMILLER |
| 12/30/08 ELECTRICAL REVISION UNDER "B",CALLED |
| NICK./WRT. |
| 12-19-08 REV #7 $80 ELEC "REQUEST TO PUT MAIN |
| PWOER UNDERGRUND FROM ELEC POLE USING #4 |
| THROUGHOUT ALL" WL |
| 12-19-08 NICK BESSENROTH PICKUP LANDSCAPE PLAN WL |
| 12/18/08 - LANDSCAPE PLAN APPROVED AND READY FOR |
| P/U. CALLED CONTRACTOR FOR P/U. FILED UNDER B. ~MC |
| 12/18/08 NICK P/U DENIED ELEC PLANS SPALMER |
| 12/18/08 NICK P/U DENIED LANDSCAPE PLANS SPALMER |
| 12-18-08 SAM LUTZ PICKUP MECH SUBMITTAL (DATED |
| 12-17-08) WL |
| 12/18/08 CALLED LEFT A MESSAGE WITH SAM FOR P/U . |
| PLANS IN BOX (S) HM. |
| 12/17/2008 ***ROUTED TO INCOMING PER HAROLD MOSER |
| MMILLER**** |
| 12/17/2008 MECHANICAL SUBMITTAL NO FEE (IN |
| INSPECTOR'S REQUEST PER HAROLD MOSER ACCORDING TO |
| CUSTOMER) EXPLAINED TO CUSTOMER THAT ONCE PLANS |
| EXAMINER GETS A PLANS AND REALIZE THAT THIS A |
| REVISION INSTEAD OF A MECHANICAL SUBMITTAL THEN |
| CUSTOMER WOULD HAVE TO FOR REVISION ROUTED TO |
| HAROLD MOSER'S DESK MMILLER |
| 12/16/08 LANDSCAPE REV $80 SPALMER |
| 11-24-08 REV #5 $60 "PLUMBING RISER DIAGRAM DAVID |
| BISHOP REQUESTED" WL |
| 9/7/08 - ZONING FAILED. CALLED CUSTOMER FOR P/U. |
| FILED UNDER B. ~MC |
| 08/29/2008 LANDSCAPE SUBMITTAL (NO FEE) MMILLER |
| 8/12/08 ELECTRICAL REVISION READY FOR P/U CALLED |
| SPOKE TO BUZ FILED UNDER "B" SLS |
| 08/11/2008 FOLLOW-UP CALL CALLED CUSTOMER (NO |
| ANSWER ) FOR DENIED REVISION THAT WAS SUBMITTED ON |
| 06/17/2008 IS READY FOR P/U FILED UNDER "A" |
| MMILLER |
| |
| 7/24/08 ELECTRICAL REVISION UNDER "B"./WRT. |
| 06/30/2008 ELECTRICAL REVISION # 04 FEES $ 60.00 |
| MMILLER |
| |
| 6-20-08 F MECH/REV CALLED SAM P/U "B" TG. |
| 06/17/2008 MECHANICAL REVISION # 03 FEES $ 60.00 |
| MMILLER |
| 5/19/08 NICK P/U REV #1 & #2 SPALMER |
| 5/17/08 CALLED P/U REV #1 AND #2 UNDER "B" AM |
| 5/13/08 BLDG REV PGT WINDOWS AND DOORS INSTEAD OF |
| PELLA $70 SEW |
| 5/12/08 BLDG REVISION P/U & RESUBMITTED AS NO FEE |
| PER LUIS SLS |
| 5/8/08 CALLED P/U UNDER "B" AM |
| 04/29/2008 BLDG REVISION # 01 FEES $60.00 MMILLER |
| 1/7/08 PERMIT P/U BY NLICK, NOC BEING FAXED IN, |
| INSP. HOLD APPLIED AJP |
| 1/3/08 CALLED P/U UNDER "B" **LARGE BINS** AM |
| 12/28/07 WILL NEED NOC TO BE RE-RECORDED, EXPIRED |
| PER FS 713.13(2). DV PALMER |
| 12/26/2007 2ND RESUB PLANS PLUS APP MMILLER |
| 12/10/07 DENIED RESUB PLANS/APP/COMMENTS P/U BY |
| NICK AJP |
| 12/7/07 CALLED P/U UNDER "B" **LARGE BINS** AM |
| 11/09/07 1ST RESUB NO FEE SPALMER |
| 10/10/2007 DENIED PLANS PLUS APP P/U BY NICK |
| MMILLER |
| CALLED P/U UNDER "B" ***LARGE BINS*** AM |