| Miscellaneous Information / Notes |
| ADDITION OF MASTER BATHROOM |
| |
| |
| |
| |
| 2-29-08 MILTON GREY PICKUP PERMIT WL |
| 2-28-08 LEFT MESSAGE ON MILTON'S CELL. PERMIT |
| UNDER "G". JG. |
| 2/27/08 - SENT TO JG - 3RD FLOOR ADQ |
| 2/26/08 - SENT TO ADQ - 5TH FLOOR CJH |
| 02/26/2008 6TH RESUB PLANS PLUS APP MMILLER |
| 2-26-08 MET W/ MILTON GREY. JG. |
| 2-21-08 MET W/ MILTON GREY. JG. |
| 2-21-08 MILTON GREY PICKUP PLANS WL |
| 2-20-08 TALKED TO MILTON GREY. PLANS UNDER "G". |
| JG. |
| 02/08/2008 5TH RESUB PLANS PLUS APP MMILLER |
| 12/14/07 DENIED RESUB PLLALNS/APP/COMMENTS PL/U BY |
| MILTON GREY AJP |
| 12-12-07 LEFT MESSAGE ON CONTRACTOR'S CELL. PLANS |
| UNDER "G". JG. |
| 12-12-07 PLANS RECEIVED TODAY. JG. |
| 11/8/07 - ROUTED TO "E" - BT CJH |
| 11/7/07 - SENT TO CJH FOR PROCESSING - 3RD |
| FLOOR.ADQ. |
| 11/6/07 - SENT TO ADQ - 5TH FLOOR CJH |
| 11/01/2007 4TH REUB PLANS PLUS APP MMILLER |
| |
| 10-24-07 MET WITH ENGINEER LUIS LOPEZ AND LUIS |
| CANALES TO GO OVER PLANS. JG. |
| 10/09/07 DENIED RESUB PLANS/APP/COMMENTS P/U BY |
| MILTON AJP |
| 10-3-07 TALKED TO MILTON GREY. ENGINEER NEEDS TO |
| PAY FOUR TIMES THE PLAN REVIEW FEE. PLANS UNDER |
| "G". JG. |
| 9/7/07 2ND RESUB $ SPALMER |
| 7/31/07 RESUB APP / PLANS/COMMENTS P/U BY MILTON |
| GREY AJPP |
| 7-30-07 TALKED TO MILTON GREY. PLANS UNDER "G". |
| JG. |
| 07/05/2007 2ND RESUB PLANS PLUS APP MMILLER |
| 6/19/07 PU BY MILTON SEW |
| 6-18-07 TALKED TO MR. GREY. PLANS UNDER "G". JG. |
| 5/23/07 1ST RESUB W/PLANS & APPL NO FEE SEW |
| 4/27/07 MILTON P/U DENIED PLANS SPALMER |
| 4-26-07 TALKED TO CONTRACTOR. PLANS UNDER "G". JG. |