| Miscellaneous Information / Notes |
| CONSTRUCT 2 STORY CBS SFR |
| **PROVISO**SEPARATE PERMIT SHUTTERS |
| |
| |
| |
| 9/12/07 APPROVED MECH. REV. P/U BY DOUG AJP |
| 9-10-07 P MECH/REV. CALLED DOUG P/U "S" TG. |
| 8/28/07 MECH REV $60 SPALMER |
| 8/7/06 APPROVED PLBG REV. P/U BY FRANK(NAT HEALY) |
| AJP |
| 8/7/07 PLBG REV UNDER "S" JHL |
| 1/5/07 NAT P/U PERMIT SPALMER |
| 1/4/7 ISSUED CALLED CONTR **LARGE BINS** 'S' SMH |
| 1/3/7 GAVE PKG TO NAT HEALY, DUPLICATE APP NEEDS |
| HISTORIC STAMP SMH |
| 12/29/06 SUBMITTAL NEW APPLICATION IMPACT FEES AND |
| NOC NO FEE SLS |
| 12/27/06 NAT HEALY P/U DENIED PLANS SPALMER |
| ***NO RESUB FEE, IMPACT FEE/APPLICATION ONLY**SMH |
| 12/26/6 CORR, CALLED CONTR, BIG BIN'S' SMH |
| 11/28/06 PLANS SUBMITTED ON 11/20 WERE ACTUALLY |
| 1ST RESUB NO FEE, NOT SUBMITTIAL, NO PERMIT |
| APPLICATION IN PACKAGE, CALLED NAT HEALY. DV |
| PALMER |
| 11/20/06 BROUGHT IN AS SUBMITTAL NO FEE- UNTIL |
| REV/RESUB FROM 8/2/06 IS CORRECTED PER L MARTINEZ |
| FG |
| 9/11/06 NAT P/U DENIED PLANS SPALMER |
| 9/11/6 CORR, CALLED CONTR, 'S' SMH |
| 8/2/06 BLDG ELEC REV. $150 TA |
| 9-20-5 PLANS PU FOR HISTORIC APP - KAM |