| Miscellaneous Information / Notes |
| NSFR LOT 75 |
| SHUTTERS UNDER A SEPARATE PERMIT. |
| |
| |
| |
| |
| 5-20-05 PLANS UNDER "T". JG. |
| 5-20-05 SEANA P/U PLANS NFL |
| 6/6/05 1ST RESUB/PLANS + APP PT |
| 6-30-05 PLANS UNDER "T". JG. |
| 7-19-5 PERMIT PU/KIM - KAM |
| 8-3-05 REV DA |
| 8-16-05 REVISION UNDER "T". JG. |
| 8-18-05 REV P/U BY ALLISON DA |
| 8-23-5 SUBMITTAL - NO FEE - KAM |
| 9-21-05 BUILDING SUBMITTAL UNDER "T". JG. |
| 9/23/05 AIMEE PICKED UP SUBMITTAL. DVP |
| 12/29/05 2ND REVISION BROUGHT IN BY ALISON 5PGS |
| $100 FEE. LTM |
| 1/5/06 ELEC REV $60 SPALMER |
| 1/17/06 ELEC REV OK,CALLED, UNDER "T" FOR PU. DVP. |
| 1/18/06 ELEC. REV P/U BY ALISON AJP |
| 1-18-06 BLDG REVISION UNDER "T". JG. |
| 1/19/06 BLDG REV P/U BY ALLISON SWURAFTIC |
| 1/31/06 BLDG ELEC REV SEW |
| 2-15-06 BUILDING REVISION SENT TO PLUMBING. JG. |
| 2-27-06 DRAWING A-1.0 SUBMITTAL. JG. |
| 2-28-06 DWG A-1.0 SENT TO PLUMBING. JG. |
| 2/28/06REV. READY UNDER "T" JHL |
| 3/1/06 ALLISON P/U REV SPALMER |