| Miscellaneous Information / Notes |
| NEW SFD |
| |
| |
| |
| |
| |
| 2/16/07 TCO LETTER RECEIVED FROM CONTRACTOR $500 |
| GIVEN TO KEN CONRAD SLS |
| 5/3/06 MECH. REV. PU BY DAVID AJP |
| ************************************************* |
| ************************************************* |
| 3/30/05 ADDRESS ON APP READS 745 BISCAYNE DR |
| 4/4/05 GIVEN TO RANDALL G, PLANNER 822-1454 MM |
| 5/2/05 PLANS ARE IN LUIS'S OFFICE |
| 5-6-05 DONNA P/U PLANS NFL |
| 5-17-05 1ST RESUB NFL |
| 06/01/05 PER JOHN HIGGINS ADDRESS IS 749 BISCAYNE |
| DR PT |
| 6-16-05 CALLED TO PICK UP PLANS, CORRECTIONS |
| NEEDED, FILED UNDER ~~~"P"~~~ ALANGE |
| 6-17-05 DONNA P/U SUBMITTAL DA |
| 7-20-05 2ND RESUB WL |
| 7-29-05 CALLED TO PICK UP PLANS, CORRECTIONS |
| NEEDED, FILED UNDER "P" ALANGE |
| 8/1/05 DONNA P/U DENIED PLANS SPALMER |
| 8-2-5 3RD RESUB $300 - KAM |
| 8-10-05 CALLED TO PICK UP PLANS, CORRECTIONS |
| NEEDED, FILED UNDER "P" ALANGE |
| 8/12/05 DONNA P/U DENIED PLANS SPALMER |
| 8-29-05 4TH RESUB DA |
| 9-7-05 CALLED TO PICK UP PLANS, CORRECTIONS |
| NEEDED, FILED UNDER "P" ALANGE |
| 9/8/05 DONNA P/U DENIED PLANS SPALMER |
| 9-9-05 5TH RESUB WL |
| 9/14/05 DONNA TURNED IN NOC SPALMER |
| 9/20/05 PERMIT FILED UNDER 'P' LM |
| 9/20/05 DONNA P/U PERMIT SPALMER |