| Miscellaneous Information / Notes |
| CONDOMINIUM PROJECT 3 LEVELS OVER PARKING - 12 |
| UNITS - BLDG # 2 |
| |
| |
| |
| |
| 5-21-07 KEN TORRES PICKUP BLDG REV WL |
| 5/21/07 CALLED KEN TORRES FOR P/U OF REVISION AND |
| SUBMITTAL FOR MULLIONS, SGD'S AND SH WINDOWS. |
| LARGE BINS.'T'. RB |
| 5/18/07 BLDG REV LETTER TO ADDRESS REV #15 SEW |
| 5/11/07 2ND TCO DATED 5/9/07 ISSUED HHP |
| 05/11/2007 RCVD LETTER FOR TCO FEES $500.00 SENT |
| TO HAROLD PISKURA'S DESK MMILLER |
| 05/04/07 BLDG REV $60 FEE- FG |
| 4-26-07 KEN TORRES PICKUP BLDG REV #7 WL |
| 04/13/2007 BLDG REVISION FEES (REVISION PRODUCT |
| NOA) $60.00 MMILLER |
| 4/9/07 TCO ISSUED. TO C OF O BOX.KC |
| 03/30/2007 RCVD LETTER & RECPT FOR TEMPORARY TCO |
| SENT TO HAROLD PISKURA'S DESK MMILLER |
| 3/26/07 HILARY P/U REV DATED 3/14/07 SPALMER |
| 3-17-07 CALLED FILED UNDER (FEES OWED INVOICE |
| ATTACHED) **LARGE BINS** "T" JW |
| 3/8/07 SAM P/U REV DATED 1/31/07 SPALMER |
| 3/8/07 MECH/ELEC REV CALLED FOR P/U LG BIN UNDER |
| 'W' RJR |
| 03/02/2007 CUSTOMER SUBMITTED LETTER FOR OT |
| INSPECTION FEE $ 300.00 MMILLER |
| 1/31/07 MECH REVISION $ 90 SLS |
| 12/22/06 PUT OUT FRNT UNDR "W" CALLED TOM JL |
| 12/15/06 ELEC REV BLDG 2 SEW |
| 11/16/06 TOM P/U ELEC REV DATED 11/13/06 SPALMER |
| 11/13/06 ELECTRICAL REV $ 80 MMILLER |
| 11/13/06 ELECTRICAL REV $60.00 MMILLER |
| 11/8/06 PU BY DON WOODS SEW |
| PUT REVISIONS OUT FRONT **LARGE BINS** "W" CALLED |
| JL |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| 10/23/06 NEW NOC SUBMITTED SEW |
| 10/20/06 PLANS PICKED UP BY MIKE LM |
| 10/6/06 ELEC REV BLDG 1/2 RISER SEW |
| 9-15-06 CALLED FILED UNDER "T" JW |
| 7/21/06 EL.REV. .P/U BY TOM AJP |
| 7/21/06 CALLED FOR P/U "T" MRW |
| 7/19/06 FIRE REVIEW PLANS P/U BY TOM SLS |
| 7/17/06 FIRE REV FEE CHARGED ON # 04110182 PLAN |
| REVIEW WILL ADJ IF ADD'L FEES OWED PER RBROWN SEW |
| 6/30/06 PU BY TOM SEW |
| 6/23/06 MECH REV M-203/BLDG 2 $60 SEW |
| 6/20/06 CALLED FOR P/U UNDER "T"*LARGE BIN** HM. |
| 6-20-06 TOM HERR PICKUP (LG PLAN) PLANS WL |
| 6-20-06 TOM HERR PICKUP PLANS LARGE PLANWL |
| 6/19/06 REVISION FILED UNDER 'T', CALLED |
| CONTRACTOR TO STRAIGHTEN UP THE MESS OF REVISIONS |
| SUBMITTED LM |
| 6/15/06 ELEC REV BLDG 2 $60 SEW |
| 6/12/06 TOM P/U DENIED ELEC REV SPALMER |
| 6/9/06 ELEC REV UNSAT, CALLED TOM, UNDER "T"FOR |
| PU, DV PALMER. |
| 6/6/06 TOM P/U MECH REV SPALMER |
| 6-6-06 P MECH/REV. LEFT MSG. P/U "T" TG. |
| 6/1/06 MECH REV $ 60 FEE FG |
| 5/24/06 ELEC REV $60 SEW |
| 5/3/06 BLDG ELEC PLUMB MECH REV $90 SEW |
| 4/11/06 REV $230 FEE FG |
| *DO NOT ISSUE UNTIL UNITY OF TITLE * |
| 12-31-04 CALLED FOR P/U 3ROLLS BOTTOM SHELF PHK |
| |
| 1/5/5 PLANS P/U BY KERRY W DR |
| 1/19/05 1ST RESUB NO FEE PSMITH |
| 1/24/05 CHANGE OF CONTRACTOR FROM MANHATTAN TO THE |
| WEITZ $100 PT |
| 1/26/05 SUB/ALTERNATE METHOD FOR DRYER EXHAUST FAN |
| GIVEN TO NEIL PT |
| 02-28-05 CALLED FOR P/U NAM |
| 3/1/05 UNDER "M" ROLLS AND 1BOX ADARROUGH |
| 3-2-05 LARRY P/U PLANS NFL |
| 4-15-5 2ND RESUB - $2850 - KAM |
| 4-26-5 SUB SOILS TEST REPORT FG |
| 5-12-05 SUBMIT DUPL PERMIT APPL PER J WITMER OK |
| PER DEAN RUNNELS TO ADD SUBCONTRACTORS AT THIS |
| TIME & CHG $50 PER SUB WL |
| 5/27/05 PERMIT P/U BY JEFF PT |
| 6-6-05 REV $130 DA |
| 6/20/05 REV OK, CALLED CONTR, 'T' SMH |
| 7-12-05 SUBMITTAL BLDG DRAWINGS DA |
| 8-16-05 NO FEE BLDG SUBMITTAL SHORING DRAWINGS WL |
| 8-29-5 BLDG REV $70 - KAM |
| 8-29-5 3 BLDG SUBMITTALS & LETTER PU/SILVANA- KAM |
| 9-7-05 SUBMITTAL (1) DA |
| 9-08-05 CALLED FILED UNDER "T" JW |
| 9/8/05 REV/BLD P/U BY SHAUN PT |
| 9-8-05 SUBMITTAL (2) DA |
| 9/16/05 REV/ELEC PLUMB MECH $650 PT |
| 9-28-05 SUBMITTAL DA |
| 11/10/05 SUBMITTAL STORING & RESTORING COMPLIANCE |
| LETTER BLDG #2 NO FEE LMILLER |
| 11/10/05 SUBMITTAL MECH EQUIP NO FEE LMILLER |
| 12/10/05 SUB/BLDG (BLDG 2 ROOF POUR) PT |
| 12-29-05 NO FEE SUBMITTALS BLDG 2 TRUSSES ALSO |
| APPLIANCE SUBMITTAL/WINDOW SHOPS/ FIRE- PROOFING/ |
| DIANE WAS ASKED TO INITAL DATE CHGS & FINISH |
| FILLING OUT SUBMITTAL FORM..DID NOT COMPLETE FORM |
| & DID NOT INITIAL ALL CHGS WL |
| 1-5-06 REV/MEP'S/FIRE CALLED FOR P/U BOTTOM SHELF |
| FOUR ROLLS OF PLANS PHK |
| 1/11/6 SUBMITTAL TO JAH DESK SMH |
| 1-11-06:SUBMITTAL FAILED, LOCATED IN CARDBOARD BOX |
| MARKED "WEITZ." JAH |
| 1-13-06 BLDG/ELEC/MECH SUBMITTAL BLDG 2 WL |
| 1/26/6 CORR SUBMITTALS, CALLED CONTR, BIN 'THE |
| WEITZ COMPANY' SMH |
| 1/27/06 ALL PLANS/APPS P/U BY DIANE AJP |
| 2-7-06 SUBMITTAL TO HHP BY RB NFL |
| 2-8-6 DRY-IN PLAN REVIEWED AND STAMPED,FILED |
| UNDER W, RSN1968 |
| 2/8/06 SUBMITTAL PU BY TOM SEW |