| Miscellaneous Information / Notes |
| NEW CONSTR CITYSIDE BLDG 4C UNITS 1-6 |
| "B" ELEVATION |
| |
| |
| |
| |
| |
| |
| 2/27/04 PD $2759.54 BZ232039 BALANCE $6438.93 SPAL |
| 6/10/04 1ST RESUB NO FEE PSMITH |
| 3/10/04 2ND RESUB PLANS + APP PT |
| 3/18/05 DENIED/CALLED/UNDER 'W' RM |
| 3/21/05 BRIAN P/U DENIED PLANS SPALMER |
| 3/22/05 3RD RESUB $834.26 SPALMER |
| 3/23/04 SENT TO ZONING RM |
| 3/25/05 CALLED/ROOFERS W.C.EXPIRED/OWES FEES/UNDER |
| 'W' RM |
| 3/30/05 DAISY P/U PERMIT SPALMER |
| 4/18/05 SOIL DENSITY TEST REPORT OK /UNDER 'W' RM |
| 5/18/5 1ST REV $60 FEE FG |
| 5/24/05 REV OK UNDER 'W' RM |
| 5/25/5 REV P/U BY BRIAN FG |
| 6/6/5 PLUMB REV $ 60 FEE FG |
| 6/25/05 PLBG REV READY UNDER W JHL |
| 6/29/5 REV P/U BY BRIAN FG |
| 9-15-05 REV (MECH) DA |
| 9/21/5 BLDG REV $60 FEE FG |
| 9/26/5 REV $80 FEE FG |
| 9.28.05 MECH REV CALLED FOR P/U UNDER 'W' RJR |
| 9/29/05 BRIAN P/U REV SPALMER |
| 10-4-5 REV $70 - KAM |
| 10/7/05 BRIAN P/U REV SPALMER |
| 10/7/05 PLUMBING REV. UNDER "W" JHL |
| 10/18/05 BRIAN P/U REV SPALMER |
| 12/1/05 REV OK/UNDER 'W' RM |
| 12/08/05 REV. P/U BY BRIAN AJP |