| Miscellaneous Information / Notes |
| BUILDING 2 STORY ADDITION AS SHOWN ON PLANS |
| |
| |
| 1//17/06 WORK COMPLETED ON 05051487 HHP |
| |
| 12/24/03 DENIED, NEED 2 COPY OF SURVEY SHOWING THE |
| LOCATION OF ADDITION CALLED OWNER FILE G MM |
| 12-24-03 E GODZISZEWSKI SUBMIT SURVEYS NO FEE WL |
| 1/7/03 PASS ZONING MM |
| 1-21-04 CALLED TO P/U "G" ALANGE |
| 2-18-04 ED GODZISZEWSKI PICKUP PLANS WL |
| 4/15/04 1ST RESUB NO FEE SPALMER |
| 4-26-04 CALLED TO PICK UP CORRECTIONS NEEDED |
| FILED UNDER "G" ALANGE |
| 4/26/04 EDWARD G P/U DENIED APPL.SH |
| 5/5/04 2ND RESUB/$50/BZ#240706/BLDG.SH |
| 5-6-04 CALLED TO PICK UP PLANS,FEES DUE |
| CORRECTIONS NEEDED, FILED UNDER "G" ALANGE |
| 5/6/04 EDWARD G P/U DENIED PLANS,PD FEES.SH |
| 5/6/04 3RD RESUB/$50/BZ#240708.SH |
| 5/7/04 PERMIT P/U ED PSMITH |
| 7/21/04 REV/BLDG BZ243858 $70 PT |
| 7-23-04 CALLED TO PICK UP PLANS, CORRECTIONS |
| NEEDED, FILED UNDER "G" ALANGE |
| 9-30-4 REV PU/EDWARD G - KAM |
| 5-25-5 VOID PERMIT-NO LONGER OWNER-LTR ON FILE |
| FROM NEW OWNER - KAM |