| Miscellaneous Information / Notes |
| 2 STORY SFR - INCLUDING DRIVEWAY. |
| FLOOD ZONE A5. NEED ELEVATION CERTIFICATE. |
| |
| PAID 30% $810.00 BZ 229045 STILL OWES $1917.00 |
| PLUS $51.00 APPROACH AND RADON BEFORE ISSUING PER- |
| MIT |
| 8/20/03 PASS ZONING MM |
| 9-12-03 CALLED CONTRACTOR. DWGS UNDER "J". JG. |
| PLANS PU/JIM 9-12-03 KAM |
| 9/18/03 1ST RESUB NO FEE PSMITH |
| 10-7-03 CALLED CONTRACTOR. PLANS UNDER "J". JG. |
| 10-7-03 CALLED ARCHITECT TO GO OVER DEFICIENCIES |
| ON DWGS. HE WAS OUT ON VACATION. JG. |
| 10/8/03 APP & PLANS PU JIM PSMITH |
| 10-16-03 2ND RE-SUB RECEIVED BY PEGGY SMITH. JG. |
| 10-21-03 DENIED PLANS (3RD TIME)UNDER "J". JG. |
| 3RD RESUB - $377.58 BZ #232671 10-23-03 KAM |
| 10-27-03 PLANS ON LUIS MARTINEZ DESK. JG. |
| 10/30/03 JIM COLE PICKED UP PLANS LM |
| 12-11-03 SENT PLANS TO LUIS MARTINEZ FOR PLUMB. & |
| ELECTRICAL RE-STAMPING. JG. |
| 4-1-4 SUBMITTAL TO JULIO - NO FEE - KAM |
| 4-1-04 SENT TO ZONING TO REVIEW SURVEY. JG. |
| 4-13-04 PLANS SENT TO ELEC. JG. |
| 4/19/04 REVISION FILED UNDER 'J' LM |
| 4/19/04 PAID FOR REV/$100/BZ#239520.SH |
| 4/22/04 ELEC/PLUMB $80 BZ240185 SPALMER |
| 5-11-4 CALLED FOR P/U "J" KSTEVENS |
| 5-18-4 REV PU/JIM - KAM |
| 6-11-4 PLANS BROUGHT IN FROM JIM COLE FOR KEN S |
| AS BUILTS-SAYS THEY ARE THE CITY COPIES - KAM |
| 6-21-4 PLANS SENT BACK - THEY ARE NOT CITY COPIES |
| THEY HAVE BEEN DENIED - SHEETS HAVE BEEN CHANGED |
| OUT SINCE BLDG PLAN REVIEW. CALLED FOR P/U "J" |
| KSTEVENS |
| 6-22-4 PLANS PU/JIM - KAM |