| Miscellaneous Information / Notes |
| ELECTRICAL UNDER FOUNDATION ONLY BUILDING UNDER |
| SEPERATE PERMIT MASTER # 02120627 |
| |
| |
| 1/6/05 ELECTRICAL OT INSPECTION REQUESTED FOR |
| SATURADY 1/8/05 $200.00 LTR CLD RICHARD PSMITH |
| 1/10/05 WEEKDAYS OT ELEC INSPEC $100 PSMITH |
| 1/12/05 PER RICHARD OWES $100 FROM 1/10/05 |
| 1/12/05 WEEKDAY OT ELEC INSPEC $200 PER RICHARD C. |
| PSMITH |
| 1/27/05 OVERTIME INSPECTIONS FOR 1/27 1/28 1/29 |
| 2/1 AND 2/2 $1000 SPALMER |
| 2/8/05 OVERTIME INSPECTION 20 HRS $1000 DR |
| 2/22/05 OVERTIME INSPECTION FEB 22/23/24/25/26 |
| $1000 SPALMER |
| 3/3/5 MAECH 3,4,5,7 & 8 OT INSPECTION $1000 |
| BZ 247643 DR |
| 4-12-05 OVERTIME INSPECTION FOR APRIL 12-16 $1,000 |
| D.A. D.R. |
| 4-29-05 OVERTIME INSPECTIONS SAT 4-30-05 5 HRS, |
| MAY 2,3,4,5, & 6 (MON-THURS) 3 HRS PER EVENING |
| TOTAL HOURS 20 $1000 BZ 248002 COPY ROUTED TO JAKE |
| LEAHY & TO HAROLD PISKURA WL |
| 5/13/05 OVERTIME INSPECTIONS MAY 14/16/17/18/19/20 |
| 20 HOURS $1000 BZ247832 SPALMER |
| 6-3-05 PER DEAN RUNNELS 20 HRS OVERTIME |
| INSPECTIONS PER LTR DATED 6-3-05 JUNE 4 5 HRS JUNE |
| 6-10 3 HRS PER EVENING OK NOT TO CHG WEEKEND RATE |
| FOR FRI 6-10 |
| BZ 248073 $1000 (20 HRS) ROUTED TO JAKE LEAHY WL |
| 8-12-05 SPECIAL INSPECTION (4) HOURS $400 TO J |
| LEAHY NFL |
| 8-13-5 OVERTIME INSPEC FOR A TOTAL OF 24 HRS $1200 |
| TO JAKE L - KAM |
| 9-30-05 OVERTIME INSPECTION 34 HRS $1,800 TO KEN |
| CONRAD & PER (KC) CUST ONLY HAD 1,700 NOT $1,800 & |
| PER KC THAT IS WHAT HE PAID DA |
| 10-14-05 RECVD LTR FROM CONTR FOR 24HRS O/T & PER |
| KEN CONRAD NO FEE & PUT LTR ON HIS DESK DA |
| 10/19/05 RECEIVED CHECK FOR $1200 FOR 24 HRS OF |
| OVER TIME INSPECTIONS COULD NOT REACH INSPECTOR TO |
| VERIFY SPALMER |
| 11/17/05 OT/TOTAL OF 20 HRS/5 DAYS EACH 4HRS |
| (11/17 11/18 11/21 11/22 & 11/23) COPY OF LTR |
| GIVEN TO HAROLD & JAKE PT |