| Miscellaneous Information / Notes |
| NEW TILT WALL SHELL BLDG SITE WORK/PAVING SITE |
| LIGHTING LANDSCAPING/ FACTORY INDUSTRIAL USE |
| |
| GRAM PICKED UP TO PAY IMPACT FEES AT PBC 6/26/01LS |
| IMPACT FEES PD PR01024224 6/28/01 SJOHNSON |
| SHOP DRAWINGS TILT WALLS 06/29/2001 LS |
| REV.#1 B,E,,P,M 6/29/01 LS NO FEE |
| OWES FOR REV FEE, FIRST REV IS NOT FREE. SEE BZ# |
| 187542.$ 380.00. DV PALMER |
| 7/10/01 GRAHAM PU DRAWINGS YD |
| 7/11/01 GRAHAM SUBMITTED RINKER SPECS. DR |
| 7/11/01 RINKER SPECS OK LS GAVE DON 1 COPY |
| 7/19/01 GRAHAM PU REVISION YD |
| REVISION $70 BZ188155 7/24/01 SJOHNSON |
| PLANS DENIED UNDER H TO FOR P/U 7/29/01 JHL |
| REV PU BY GRAHAM 8-1-01 TJ |
| REV FOR PLUMB PU BY GRAHAM 8-1-01 |
| REV FOR ELEC 9-27-01 TJ |
| ELEC REV OK UNDER "H", CALLED 10/3/01 DV PALMER |
| 10/4/01 GRAHAM PU REVISION YD |
| 10/31/01 REVISION BZ193194 $80 YD |
| ELEC REV FROM 10/31 UNDER "H" FOR PU. 11/5/01 DVP. |
| REV P/U GRAHAM BLACK 11/07/01 SJOHNSON |
| 11-14-01 SUBMITTAL FOR BUILD TJ |
| 11/16/01 REVISION BZ193749 FOR ELEC $70 YD |
| ELEC REV FROM 11/16 UNDER "H"FOR PU. CALLED,11/20/ |
| 01 DV PALMER. |
| 11/21/01 CATHERINE PU REVISION YD |
| SUBMITTAL FOR BUILD 11-29-01 TJ |
| REV P/U GRAHAM BLACK 12/7/01 SJOHNSON |
| REV #6 ELEC $110 BZ 196220 12-21-01 WL |
| REV #7 BLD BZ#197691 $60 DR |