Date |
Text |
2013-04-12 09:46:52 | PERFORMED AN IN PROGRESS INSPECTION. THE |
| FOLLOWING WAS OBSERVED: |
| |
| 1) THE FIRST TILT WALL PANEL POUR WAS |
| COMPLETED UPON MY ARRIVAL. A CREW OF |
| CONCRETE FINISHERS WERE COMPLETING WORK |
| ON THE CAST PANELS. |
| |
| 2) CONCRETE CYLINDERS WERE CAST FOR |
| FUTURE COMPRESSIVE STRENGTH TESTING. |
| |
| MET WITH THE ON-SITE BUILDING INSPECTOR, |
| JERALD SMITH, AND THE PROJECT |
| MANAGER/SUPERINTENDANTS TO DISCUSS OUR |
| POLICIES AND PROCEDURES: |
| |
| 1) ALL CONSTRUCTION DOCUMENTS MUST BE |
| POSSESS A RED CITY STAMP/PERMIT NUMBER, |
| PRIOR TO PERFORMING ANY INPECTION. |
| |
| 2) THE GC WILL ENSURE THAT THE ON-SITE |
| INSPECTOR RECEIVES THE ORIGINAL STAMPED |
| PLANS. |
| |
| 3) A WRITTEN REQUEST FOR WORK AFTER |
| HOURS SHALL BE SUBMITTED AND APPROVED BY |
| THE BUILDING OFFICIAL. ALL RESIDENTS |
| WITHIN THE 1000 FT. RADIUS SHALL BE |
| NOTIFIED. THE NORMAL WORKING HOURS ARE |
| 7AM TO 7PM,WEEKDAYS AND 8AM-8PM DURING |
| THE WEEKENDS. |
| |
| 4) ALL CITY ROW'S SHALL BE MAINTAINED |
| AND FREE OF DEBRIS. |
| |
| 5) AFTER HOURS INSPECTIONS MAY BE |
| PROVIDED AS NEEDED UPON REQUEST IN |
| ADVANCE. THE COST IS $200.00 FOR MINIMUM |
| 2 HOUR WEEKDAY INSPECTION AND $400.00 |
| FOR A MINIMUM OF 4 HOUR INSPECTION |
| PERFORMED DURING A WEEKEND. |
| |
| |