| DATE | TIME | INSPECTION / EVENT TYPE | INSTRUCTIONS / COMMENTS | | 2012-07-27 | 10:34:31 | COMMENTS | ADDED FINE ON 18-209-A START DATE: 06/05/12 FINE AMT: 100.00
|
| 2012-07-27 | 10:33:56 | AONC SENT TO LAW | |
| 2012-07-19 | 10:54:15 | AFFIDAVIT OF NON-COMPLIANCE | COMPLETED.TURNED IN FOR NOTARIZATION.
|
| 2012-06-04 | 10:36:20 | REINSPECTION FOR SM ORDER FEES | NOT COMPLIED WITH BOARDING CERTIFICATE.CUT/CLEAN AND BOARD/SECURE OF PROPERTY HAD BEEN ABATED BY CITY CONTACTORS.
|
| 2012-05-07 | 11:00:14 | CONTRACTORS INVOICE APPROVED | ANCHORS INVOICE SUBMITTED TO FINANCE
|
| 2012-05-07 | 10:58:49 | CONTRACTORS INVOICE APPROVED | BUSHOG INVOICE SUBMITTED TO FINANCE
|
| 2012-05-02 | 15:25:08 | CONTRACTORS INVOICE APPROVED | I SIGNED OFF ON CONTRACTOR (ANCHOR'S EMERGENCY BORAD-UP) ABATEMENT INVOICE.
|
| 2012-05-02 | 15:20:55 | CONTRACTORS INVOICE APPROVED | I SIGNED OFF ON CONTRACTOR (S.FL.BUSHOG) ABATEMENT INVOICE.
|
| 2012-05-02 | 10:36:00 | SPECIAL MASTER ORDER | 30 DAYS OR $100 PER DAY; NO ONE PRESENT
|
| 2012-05-02 | 10:16:23 | NOTICE OF HEARING | 05/02/2012 HEARING SCHEDULED CMALDONA
|
| 2012-05-01 | 10:16:23 | REINSPECTION | PRE-HEARING INSP SCHED CMALDONA-NOT COMPLIED IS BOARDING CERTIFICATE. THE CUT/CLEAN AND BOARD/SECURE VIOLATIONS WERE ABATED BY THE CITY'S CONTRACTORS.
|
| 2012-04-25 | 14:50:55 | COMMENTS | DEBBIE RETURNED MY CALL.I TOLD HER THAT THE REST OF THE HEDGES ALONG EAST AND SOUTH ALLEY NEEDS TO BE TRIMMED ALSO AS IT WAS NOT DONE(PER INVOICE CITY WAS ALREADY CHARGED AND I HAD THIS ON ORIGINAL WORKORDER).SHE SAID SHE WILL HAVE THEM GO BACK AND COMPLETE THE JOB.
|
| 2012-04-25 | 11:41:54 | CONTRACTORS INVOICE RECEIVED | ANCHORS INVOICE SUBMITTED TO CODE OFFICER FOR APPROVAL
|
| 2012-04-23 | 08:14:55 | CONTRACTOR | BOARD/SECURE ABATED BY CITY CONTRACTOR (ANCHORS EMERGENCY BOARD-UP).PHOTOS.
|
| 2012-04-20 | 10:47:20 | CONTRACTORS INVOICE RECEIVED | BUSHOG INVOICE SUBMITTED TO CODE OFFICER FOR APPROVAL
|
| 2012-04-16 | 08:12:19 | CONTRACTOR | CUT/CLEAN UP ABATED BY CITY CONTRACTOR (S.FL.BUSHOG).CONTRACTOR DID NOT COMPLETED ABATEMENT/I WILL CALL CONTRACTOR TO FINISH THE TRIMMING OF THE REST OF THE HEDGES.PHOTOS.
|
| 2012-04-13 | 10:06:26 | WORK ORDER FAXED TO CONTRACTOR | BUSHOG WORK ORDER FAXED
|
| 2012-04-13 | 10:00:47 | WORK ORDER FAXED TO CONTRACTOR | ANCHORS WORK ORDER FAXED
|
| 2012-04-11 | 12:47:42 | COMMENTS | I SUBMITTED BOARD/SECURE ABATEMENT WORKORDER FOR APPROVAL.
|
| 2012-04-11 | 12:46:57 | COMMENTS | I SUBMITTED CUT/CLEAN ABATEMENT WORKORDER FOR APPROVAL.
|
| 2012-04-06 | 09:06:35 | REINSPECTION | 15TH DAY REI.FROM CERT.SENT-NOT IN FULL COMPLIANCE/PHOTOS.APPEARS THAT LAWN IS CUT BUT OVERGROWN HEDGES/SHRUBS/TREES ARE NOT MAINTAINED TRIMMED.ALSO,THE PROPERTY IS NOT CLEANED UP OF ALL TRASH/DEBRIS/GARBAGE/LITTER/DEAD VEGETATION.AND BOTH STRUCTURES ARE OPEN/UNSECURED.NO CONTACT FROM ANYONE.I WILL SUBMIT ABATEMENT WORKORDERS FOR CUT/CLEAN AND BOARD/SECURE.
|
| 2012-04-04 | 16:54:30 | CERTIFIED MAIL RETURNED | 70111150000173538634-VACANT
|
| 2012-03-22 | 10:42:41 | CERTIFIED MAIL SENT | 70111150000173538634
|
| 2012-03-20 | 10:36:32 | AFFIDAVIT OF POSTING | COMPLETED.TURNED IN FOR NOTARIATION.
|
| 2012-03-20 | 10:36:13 | POSTED PROPERTY/CITY HALL | COMPLETED.PHOTO.
|
| 2012-03-20 | 10:16:23 | NOTICE OF VIOLATION | NOTICE OF VIO. RECORDED CMALDONA
|
| 2012-03-20 | 09:06:34 | CREATE INITIAL CASE RECORD | VIOLATION RECORDED CMALDONA
|
| 2012-03-13 | 09:06:35 | INITIAL INSPECTION | OWNER NOT KEEPING PREMISES CLEAN & SANITARY, GRASS/WEEDS/OTHER FLORA OVERGROWTH, CLEAN UP HALF ALLEY & STREET RIGHT-OF-WAY & SWALE ADJOINING PROPERTY, VACANT OPEN/UNSECURED STRUCTURES, BOARD/SECURE STRUCTURES TO CITY'S SPECIFICATIONS, BOARDING CERTIFICATE REQUIRED AND FAILURE TO COMPLY/AUTHORITY TO ABATE.
|