Miscellaneous Information / Notes |
INTERIOR REMODEL KITCHEN & BATH |
|
|
|
4/20/23 PERMIT ISSUED. LEM |
4/3/23 REVIEWS COMPLETE, WAITING ON UPDATED SUB |
CONTRACTOR INFO TO ISSUE PERMIT. LEM |
4/3/23, PASS FIRE, CRW |
3/31/23 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
AM |
2/7/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
2/6/23, PASS FIRE, CRW |
2/3/23 RESPONSE LETTER VALUE UPDATED TO |
$50,000.00JW |
2/3/23 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
AM |
10/11/22 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
9/16/22 RESUB RECEIVED, INCOMING COMPLETE AO |
5/1/21 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT. CP |
4/30/21 REVIEWS COMPLETED. NEED TO RESUBMIT. EQ |
4/22/21 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
PLAN REVIEW.PML |
04/21/2021 ORIGINAL SIGNED AND SEALED PAPER |
DOCUMENTS ROUTED TO STORAGE.ME |
04/21/21 RESUB UPLOADED TO PROJECTDOX, PAPER |
ORIGINALS ROUTED TO ME. INCOMING COMPLETE AO |
4/20/21 RESUB TO ADDRESS DENIED COMMENTS, ROUTED |
TO INCOMING. AM |
3/27/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
2/23/21 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
PLAN REVIEW.PML |
02/18/2021 ORIGINAL SIGNED AND SEALED PAPER |
DRAWING ROUTED TO STORAGE.ME |
02/18/21 PLANS UPLOADED, INCOMING COMPLETE AO |
02/18/21 UPLOADED TO PROJECTDOX. PAPER ORIGINALS |
ROUTED TO ME AO |
02/18/2021 ROUTED TO INCOMING SPALMER |
12/09/20 WAITING ON PAYMENT AT SUSAN'S DESK JO. |