Miscellaneous Information / Notes |
60-INSTALL 130FT OF 3-1.5" HDPE CONDUIT AT THE |
INTERSECTION OF SAPODILLA & EVERNIA ST. |
|
CONTRACTOR: LEVEL 3 COMMUNICATION, JASON CALDWELL, |
954-258-2267 |
SUB: CABLE WIRING SPECIALIST INC, MICHELLE GUZMAN, |
954-893-0501 |
START DATE: 06-15-2020 |
DURATION: 60 DAYS |
END DATE: 08-14-2020 |
DO NOT PARK ON THE SIDEWALK. BAGGING OF PARKING |
METERS IS REQUIRED WHEN BLOCKING PARKING STALLS. |
R/W & S/W RESTORATION PER CURRENT CITY STD. COPY |
OF BORE LOGS & AS-BUILTS REQUIRED. LIGHTED |
BARRICADES REQUIRED IF EQUIPMENTIS LEFT IN ROADWAY |
OR PARKING STALL AFTER DARK OR OVER NIGHT. CONTACT |
JANICE TARBILL 561-494-1079 FOR ALL CITY LOCATES. |
ALL TYPE I BARRICADES TO HAVE BALLASTS OVER BOTTOM |
RAILS. NO WORK ALLOWED BETWEEN |
7:00AM-9:00AM&4:00PM-6:00PM. ALL FOLLOWING |
INSPECTIONS MUST BE CALLED IN (LISTED ON THE BACK |
OF THE PERMIT): B800,801,802,803,804,805 |
PLEASE BE SURE TO FOLLOW THESE SPECIAL CONDITIONS |
(LISTED ON THE BACK OF THE PERMIT): |
A,B,C,D,E,F,G,H,I,J,K,L,M600,603,660 |