Miscellaneous Information / Notes |
CONSTRUCTION OF 25 STORY LUXURY RESIDENTIAL TOWER |
CONDOMINIUM |
FOUNDATION PERMIT #18040645 |
|
|
|
|
7/18/23 EXTENDED TCO ISSUED UNTIL 10/20/23 REG |
7/17/23 RECEIVED REQUEST TO EXTEND TCO ATTCHED REG |
5/31/23 PHASE 2 TCO ISSUED FLS 16 - 23 ATTACHED |
REG |
4/20/23 PHASE 1 TCO ISSUED FLS B - 15 ATTACHED REG |
4/17/23 PARTIAL STOCKING CERT. ISSUED FOR BASEMENT |
THROUGH FLOOR 15 EXCLUDING UNIT 1404. REG/KP |
4/17/23 RECEIVED REQUEST FOR STOCKING LEVELS UP TO |
15 EXCLUDING UNIT 1404 FEE PAID REG |
2/11/20 PLANS IN FILENET. LEM |
9/13/19 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, NEEDS TO SUBMIT ORIGINAL |
APPLICATION, NEEDS TO PAY REMAINING FEES, NEEDS TO |
PICK UP PERMIT CARD. LEM |
8/15/19 MECH.PASSED WITH HOLD.OK TO ISSUE,CONTACT |
[email protected]. C.C. |
8/12/19 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
7/26/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
7/8/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/5/19 REDUCED VALUATION FROM $91,000,000.00 TO |
$86,100,000.00. THE FOLLOWING WERE DEDUCTED: |
CIVIL-$1.2M, FIRE SPRINKLER-$1.2M, FIRE |
ALARM-$.2M, LANDSCAPE $1.3M, GENERATOR-$.3M, |
POOLS-.5M, SITE WALLS-.15M & IRRIGATION-.05M |
($4.9M TOTAL) |
5/30/19 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
5/8/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
5/8/19 WAITING ON CORRECTED SHEETS FROM APPLICANT. |
LEM |
4/14/19 RESUBMIT REMINDER SENT. CP |
3/14/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
02/21/2019 MICHAEL SUBMITTED THRESHOLD DOCS ROUTED |
TO SHILL JS |
1/14/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
1/14/19 WAITING ON CORRECTED SHEETS TO BE EMAILED |
FROM APPLICANT. LEM |
1/14/2019 SI FOR PROJECT ERIC SEARCH PE 54984 |
THORTON TOMASETTI 786-385-1518 SEE ATTACHMENTS REG |
12/21/18 PLAN REVIEW COMPLETE, APPLICANT INVITED |
TO RESUBMIT. CP |
9/17/18 APPLICANT UPLOADED PLANS & PAID FEES. |
INCOMING COMPLETE. CP |
9/4/18 RETURNED TO ALLOW APPLICANT TO ADD |
ADDITIONAL DOCUMENTS. CP |
9/1/18 APPLICANT UPLOADED PLANS, WAITING ON FEES. |
CP |
8/30/18 APPLICANT INVITED TO UPLOAD PLANS & PAY |
FEES. CP |
8/30/18 CUSTOMER HAS MEETING WITH ROBERT AND ABO'S |
TO DISCUSS SCOPE OF PROJECT, PERMITS, AND VALUE |
RES |