Miscellaneous Information / Notes |
CONSTRUCTION OF NEW ATHLETIC FACILITY |
|
|
08/31/2017 MAGAN PICKED UP CO. RL |
|
08/30/2017 CERTIFICATE OF OCCUPANCY PRINTED AND |
PLACED AT FRONT COUNTER, FILED UNDER "H" WITH COPY |
SENT TO SCANNING. MM |
8/18/17 MEGAN P/U TCO NATALEE |
7/31/17 TCO READY, UP FRONT IN BOX, ATTACHED WITH |
APPLICATION, MUST PAY FEE. SAK |
7/28/17 4:20PM - SPOKE TO SEAN(?) PM ON SITE. HE |
ADVISED KEN HAD GIVEN THEM A VERBAL TCO THIS AM |
AMD ADVISED HIM TO FILR THE PAPERWORK IN ORDER TO |
GET THE TCO IN HAND. NOTE, NO FIRE FINAL IS POSTED |
EITHER. SPOKE TO RAY CARANNCI AND HE IS OK WITH |
TCO, HOWEVER, REQUIRES A COUPLE ITEMS PRIOR TO CO |
BEING ISSUED. DH |
7/28/17 CALLED MONICA AND MEGAN AT HEDRICK |
BROTHERS AND EXPLAINED THAT ADA NEEDS TO BE 100% |
IN ORDER FOR THE TCO TO BE ISSUED. TCO FORM GIVEN |
TO STEVE K. DH |
6/7/17 SET P/U BY CONTRACTOR SH |
6/7/17 FOUND SET AT FRONT COUNTER; AT SH DESK |
PENDING RESPONSE FROM CONTRACTOR |
9/23/16 BRETT P/U PERMIT SPALMER |
9/23/16 ISSUED, NOTIFIED APPLICANT, 2 CONTRACTOR |
SETS IN LARGE BIN 'H', FILE SET ROUTED TO RECORDS |
SH |
9/22/16 RESUB ADDRESSING COMMENTS AND IMPACT ASM |
9/21/16 APPLICANT FIXED SET #2 (ELEC) AND ADDED |
ZONING SITE PLAN; WILL FORMALLY RESUBMIT AFTER |
TRAFFIC AND IMPACT SH |
9/21/16 CONTRACTOR CHECKED OUT ONE SET OF PLANS |
FOR IMPACT FEES SH |
9/20/16 APPLICANT NOTIFIED THAT PLAN REVIEW IS |
COMPLETE, PLANS REMAIN IN C39. LEM |
9/16/16 THE THIRD SET DOES NOT MATCH SET #1; PUT |
REVIEW ON HOLD AND NOTIFIED CONTRACTOR. PROVIDE |
CONTRACTOR WITH THE THREE SETS TO CONFIRM ALL |
THREE SETS ARE IDENTICAL. SH |
9/7/16 RE-SUB TO C39 PRIOR TO ENG REVIEW. SAK |
8/17/16 PASSED BY FIRE, RETURNED TO C39.PML |
8/3/16 RE-SUB BACK TO C39. SAK |
7/27/16 DENNIED BY PLUMB/GPJ RETURN TO C39 |
7/15/16 PASSED BY FIRE, RETURNED TO C39.PML |
6/30/16 RESUB ADDRESSING COMMENTS ASM |
6/29/16 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
RESUBMIT, FILED ON TOP OF CABINET ABOVE LARGE |
DENIED "H" APPLICATION IS MISSING. CP |
06/29/2016 ENG PASSED MGONZALEZ |
5/28/16 SENT THRESHOLD DOCS VIA EMAIL TO |
[email protected] SH |
5/10/16 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
C39.PML |