Miscellaneous Information / Notes |
"LOFTIN PLACE" CONSTRUCTION OF 8 LEVEL APT BLDG |
259 UNITS & ATTACHED 7 LEVEL PKG GARAGE |
|
|
|
|
|
|
5/3/16 CO READY FOR PICK UP "K" SEW |
1/21/16 FULL TCO ISSUED. EMAILED TO NEYITA. |
ORIGINAL PLACED IN FILE UNDER "K" DH |
11/10/15 NEYITA P/U TCO. RB |
11/10/2015 RECEIVED REQUEST FOR TCO ROUTED TO |
RBROWN & SCANNED INTO THIS PERMIT NSD |
10/20/15 RECEIVED REQUEST FOR STOCKING CERTIFICATE |
GIVEN TO KEN CONRAD & SCANNED TO THIS PERMIT |
SPALMER |
6/22/15 RESHORING DRAWINGS FOR PEDESTRIAN BRIDGE |
SUBMITTED OK BY JG. LWL |
3/9/15 SUBMITTAL OK CALLED SCOTT. SUBMITTLE UP |
FRONT IN BOX (K) HM. |
2/19/2015 REVISION SUBMITTED. LWL |
1/16/15 PLANS IN FILENET. CP |
10/8/14 PERMIT P/U BY VIKKI, MS |
10/7/14 PEDDS APPROVED, APPLICANT INVITED TO |
DOWNLOAD PLANS VIA PROJECTDOX, STILL NEEDS TO COME |
IN AND GET PERMIT CARD. CP |
10/6/14 PEDDS GIVEN TO SKENNEDY. CP |
10/6/14 SUBMITTAL OF PEDDS GIVEN TO CAROLINE PUELL |
SPALMER |
10/5/14 EMAILED PEDDS REQUIRED. CP |
10/3/14 IMPACT FEES OK SH |
10/03/2014 RESUB - IMPACT FEES PAID RECEIPTS WITH |
PLANS. MM |
9/30/14 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
SUBMIT IMPACT FEES, EMAILED APPLICANT. CP |
9/30/14 AMENITIES AREA NOT APPROVED. NEED DESIGN |
REVISION. WJ |
9/24/14 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
CP |
9/12/14 APPLICANT NEEDS TO RESUBMIT, APPLICANT |
INFORMED VIA PROJECTDOX. CP |
7/30/14 APPLICANT UPLOADED PLANS ADRESSING DENIED |
COMMENTS.***PLANS VERSIONED**** INCOMING COMPLETE. |
CP |
6/23/14 EMAILED REMINDER FOR RESUBMITTAL. CP |
5/23/14 - APPLICANT NEEDS TO RESUBMIT, APPLICANT |
INFORMED VIA PROJECTDOX. CP |
4/23/14 - FAILED FIRST ELECTRICAL REVIEW. EACH |
PAGE IS MARKED WITH ITS RESPECTIVE DEFICIENCIES. |
(MA) |
3/24/14 EMAILED J HUNTER & M OROPESA RE: FINANCE |
HOLD SH |
3/12/14 PRESCREEN PASSED. REVIEWS ASSIGNED. |
APPLICANT NOTIFIED VIA EMAIL. RJR |
3/6/14 PRESCREEN FAILED. NEED COOLING/HEAT LOAD |
CALCULATIONS, ENERGY CALCULATIONS AND PRODUCT |
APPROVALS. APPLICANT NOTIFIED VIA EMAIL. RJR |