Miscellaneous Information / Notes |
2 STORY NSFR - LOT 5-6-7-8 |
|
9-9-03 CALLED CONTRACTOR. DWGS UNDER "R". JG. |
8/12/03 PASS ZONING MM |
9/10/03 RICHARD M P/U DENIED PERMIT.SH |
10-2-03 1ST RESUB NFL |
10-20-03 NEED IMPACT FEES. DRAWINGS UNDER "R". JG. |
10-20-03 CONTRACTOR BROUGHT IMPACT FEE RECEIPT. JG |
1/16/04 BLDG SUBMITTAL NO FEE PSMITH |
2-2-04 BLDG SUBMITTAL UNDER "R". JG. |
2/14/04 REV/MECH BZ237649 $60 PT |
2/19/04 REV/ELEC BZ237650 $70 PT |
2-14-04 MECH REV CALLED FOR P/U UNDER R PHK |
2/25/04 REV/ELEC P/U BY MARC OXFORD PT |
2/25/04 REV/MECH P/U BY MARC OXFORD PT |
3/1/04 CALLED MEL FOR PICK UP, UNDER"R"./WRT. |
3/2/04 ELEC REV P/U MARC PSMITH |
3/9/04 REV/ELEC BZ238324 $70 PT |
3-10-04 BLDG REV BZ 238583 $60 NFL |
3/15/04 BLDG SUBMITTAL NO FEE PSMITH |
3-15-04 CALLED CONTRACTOR. REVISION UNDER "R". JG |
3/16/04 REV/BLDG P/U BY MEL BAKER PT |
3/16/04 ELEC REV UNDER"R"./WRT. |
3/16/04 REV/ELEC P/U BY MEL BAKER PT |