Miscellaneous Information / Notes |
MASTER#13070994 ELECTRIC FOR 9 STORY HOTEL |
"MARRIOTT RESIDENCE INN" |
|
|
|
|
|
|
1/9/15 INSPECTION REQUEST FOR 1/10/15 $800 OKAY |
PER DHARVEY & SCARDIELLO SEW |
|
4-9-2014 SAME DAY INSPECTION $100 FEE NOT ADDED, |
BECAUSE THEY HAVE A BALANCE OF $400 AVAILABLE - |
BALANCE AVAILABLE IS NOW $300 - DRF |
|
3/28/14 3/29 INSPECTION CANCELLED - DRF |
|
3/27/14 REQUESTED SATURDAY 3/29 INSPECTION; $400 |
FEE ADDED AND PAID - DRF |
|
3/20/14 REQUESTED SATURDAY 3/22 INSPECTION; $400 |
FEE ADDED - DRF |
3/15/2014 - WEEKEND INSPECTION PERFORMED, PAID FOR |
3/12/14 RECEIVED EMAIL REQUEST FOR MARCH 15 OT |
INSPECTION |
|
3/7/14 RECEIVED EMAIL REQUEST FOR MARCH 8 OT |
INSPECTION - INSPECTION MADE ON 3-8 - FEES EVEN - |
DRF |
|
2/27/2014 CONFIRMATION EMAIL READY TO PAY FEES; |
ADDED FEES |
|
2/25/14 RECEIVED EMAIL REQUEST FOR OT INSPECTION |
FOR MARCH 1, 2014 (SLAB INSP) |
|
2/7/14 REC'D EMAIL REQUESTING AN OVERTIME |
INSPECTION FOR FEB 8, 2014 (SLAB INSPECTION) ADDED |
FEES AND ROUTED REQUEST TO DHARVEY SEW |