Code Enforcement Detail |
Case Number |
CE15060581 |
*zones* |
|
Case Date |
2015-06-15 |
priority |
|
Type |
DISC |
Status |
W - W |
Description |
DISCOVERED BY INSPECTOR |
Officer |
7003 |
Operator |
pyusko |
Property On Case |
Property ID |
7443432116 |
Owner |
COURTYARDS IN CITYPLACE CONDOMINIUM |
Property Address |
630 S SAPODILLA AVE |
Owner Address |
720 S SAPODILLA AVE |
City/State/Zip |
WEST PALM BEACH FL 33401 |
City/State/Zip |
WEST PALM BEACH FL 33401 |
|
|
Phone |
|
|
Case Description |
WORK DONE WITHOUT PERMITS. | | STOP WORK ORDER ISSUED 4/2/15. |
|
|
Violation Code(s) |
1: 105.1 -- FAILURE TO SECURE BLDG PERMIT |
|
|
Inspections/Events Detail |
DATE | TIME | INSPECTION / EVENT TYPE | INSTRUCTIONS / COMMENTS | 2016-02-12 | 07:58:36 | COMMENTS | ASSISTANT BUILDING OFFICIAL DOUG HARVEY CONSIDERS THE CASE COMPLIED. HE ADVISED THAT THEY HAVE PROVIDED THE NECESSARY DRAWINGS, OBTAINED THE NEEDED PERMITS AND THEY ARE MAKING GOOD PROGRESS. IN THE SPIRIT OF COOPERATION HE HAS MARKED THE AFFIDAVITS AS COMPLIED AND HE ANTICIPATES COMPLETION OF THE PERMITTED WORK OVER THE COURSE OF THE NEXT COUPLE MONTHS.
| 2016-02-11 | 10:15:52 | COMPLY CASE | COMPLIED 12/15/15 AND 2/8/16 PER DOUG HARVEY. WORK IS UNDERWAY & CONTINUING. RESIDENTS MUST BE MOVED OUT AND IN TO COMPLETE SATISFACTORY PROGRESS.
| 2015-12-15 | 14:04:48 | REINSPECTION FOR SM ORDER FEES | | 2015-11-03 | 13:10:22 | REINSPECTION (ADDITIONAL) | | 2015-09-16 | 14:05:37 | SPECIAL MASTER ORDER | 90 DAYS TO COMPLY, WHICH INCLUDES GETTING PLANS DRAWN AND APPROVED BY CITY AND THEN ANOTHER 90 DAYS FROM THERE (180 DAYS TOTAL) TO HAVE ALL WORK COMPLETED INCLUDING INSPECTIONS. MICHAEL GELFAND, ESQ ATTENDED HEARING.
| 2015-09-16 | 08:35:03 | NOTICE OF HEARING | 09/16/2015 HEARING SCHEDULED PYUSKO
| 2015-09-11 | 08:35:03 | REINSPECTION | PRE-HEARING INSP SCHED PYUSKO
| 2015-09-04 | 13:10:05 | REINSPECTION FOR SM ORDER FEES | | 2015-08-27 | 14:43:33 | COMMENTS | LAW DEPT ADVISED THAT, BECAUSE NOV WAS NOT MAILED TO OWNER ON PAPA, CASE MUST START OVER AGAIN AND FOLLOW DUE PROCESS.
| 2015-08-27 | 08:35:03 | NOTICE OF VIOLATION | NOVCSDFINE PRINTED BY PYUSKO
| 2015-08-05 | 16:13:07 | NOTICE OF HEARING | 08/05/2015 HEARING SCHEDULED PYUSKO
| 2015-08-05 | 13:07:40 | SPECIAL MASTER ORDER | 30 DAYS TO OBTAIN A PERMIT AND ALSO STATUS HEARING ON 9-16-15 AND 90 DAYS TO FULLY COMPLY, WHICH INCLUDES INSPECTION, ETC OR $100 PER DAY.
| 2015-07-31 | 16:13:07 | REINSPECTION | PRE-HEARING INSP SCHED PYUSKO
| 2015-07-01 | 16:13:07 | NOTICE OF VIOLATION | NOVCSDFINE PRINTED BY PYUSKO
| 2015-06-16 | 15:04:47 | REINSPECTION | | 2015-06-15 | 15:04:47 | INITIAL INSPECTION | WORK DONE WITHOUT PERMITS. STOP WORK ORDER ISSUED 4/2/15.
| 2015-06-15 | 15:04:47 | CREATE INITIAL CASE RECORD | VIOLATION RECORDED PYUSKO
|
|
|